Skip to main content
24/7 Emergency(602) 675-1555
Tempe Permit

Can a Tempe business open with a temporary certificate of occupancy? City Code 8-111

Verified October 4, 2026
In Short

Sometimes. Tempe City Code 8-111.3 lets the building official issue a temporary certificate of occupancy before all permitted work is finished, if that portion will be occupied safely. Each is limited to 30 days, a permit gets at most three, and Table 2-A lists $1,006 for the first 30 days or each extension.

Official Source
Tempe City Code Section 8-111: Certificate of occupancy (Municode)
Tempe City Code 8-111 (Tempe Administrative Code, Certificate of occupancy); Appendix A, Table 2-A
“Temporary Certificates of Occupancy shall be limited to 30 days in length and there can be no more than three (3) Temporary Certificates of Occupancy issued for any permit”
Applies to:
Owners, tenants, general contractors and plumbing contractors opening a new or changed commercial space in Tempe
Official fee:
Temporary certificate of occupancy: $1,006.00 for the first 30 days or each 30-day extension, up to 90 days (Tempe City Code Appendix A, Table 2-A, version dated 7-1-26)
In force:
Tempe Administrative Code, City Code 8-111 and 8-110 (last amended by Ord. O2026.24, 2026-06-04); Appendix A, Table 2-A
Last verified:
October 4, 2026, against the official page

A lease start date and a certificate date are not the same date. In Tempe the certificate comes from the building official, and the final plumbing inspection is one of the things standing in front of it. When the rest of the job is late, a temporary certificate is the pressure valve, with a short clock and a price.

What does Tempe City Code 8-111 say?

Section 111.1 says a building or structure "shall not be used or occupied in whole or in part," and a change of occupancy "shall not be made," until the building official has issued a certificate of occupancy. An exception says certificates "are not required for work exempt from permits in accordance with section 105.2."

Section 111.2 says the certificate issues after the building official inspects and finds no violations of the Administrative Code, the Tempe Construction Codes or other laws the Building Safety Division enforces. For a building permit issued under the International Building Code it lists the permit number, address, portion covered, use and occupancy, type of construction, design occupant load, whether a sprinkler system is required and any special stipulations.

Section 111.3 is the temporary certificate. The building official may issue one "before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely." The official sets any conditions and the time period. The fee in Table 2-A is paid before issuance. Then the limit in the quote above applies: 30 days each, no more than three per permit.

Section 111.4 lets the building official suspend or revoke a certificate in writing if it was issued in error, on incorrect information, or where the building violates a code or ordinance.

Section 111.5 lets the building official issue a certificate of completion for a building or structure "permitted as a basic or shell building which cannot be occupied." The permit holder may request the resulting letter of compliance after a final inspection of the building and the plumbing and other systems shown on the approved plans. The letter "does not authorize the occupancy of the building or structure."

What do the key terms mean?

  • Final inspection. Section 110.3.2 says it is made after all work shown on the construction documents is completed, with systems under the prescribed tests when applicable. Section 110.6 requires a final inspection and approval "prior to any occupancy or use."
  • Temporary certificate. Permission to occupy a safe portion before the whole permit is finished. The code does not define "safely"; a reading is that the official decides case by case.
  • Letter of compliance. The 111.5 document for a shell building. It records finished work. It is not permission to move in.
  • Table 2-A. The flat fee table in Appendix A of the City Code. Fees adjust each July 1 by CPI, according to the table's footnote.

Who does this cover?

Anyone opening a new space or changing the use of an existing one in Tempe: owners, tenants, general contractors and plumbers who finish last.

It does not apply to work exempt from permits. The 111.1 exception says no certificate is needed for work exempt under 105.2, such as a like-for-like water heater replacement in a single family home.

Quick check: which document do you need?

SituationDocumentWhy
Space finished, final inspections approvedCertificate of occupancy111.2
Open now, a few items unfinished and the space is safeTemporary certificate, 30 days111.3
Needs a second monthSecond temporary certificateUp to three per permit
Shell building with plumbing roughed in, no tenantCertificate of completion or letter of compliance111.5, does not allow occupancy
Repair that was exempt from a permitNo certificate111.1 exception
Meter box lid buried below finished gradeHeld up33-39

What does this look like in real life?

A restaurant with an unfinished patio. The kitchen, restrooms and grease device passed. The patio hose bibs have not been inspected. The owner asks for a temporary certificate for the dining room. If granted, it runs 30 days at $1,006. Three in a row would total $3,018 in Table 2-A fees, which is simple arithmetic on the table, not a rate the city quotes.

A salon moving into a strip center. Plumbing is signed off and the final building inspection is done. A full certificate issues. No temporary document is needed.

The edge case: day 91. A tenant takes a first temporary certificate, then a second, then a third. The code allows no more than three per permit and Table 2-A says "up to 90 days." After the third, the code gives that permit no further temporary certificate, so the work has to be finished and the full certificate issued.

A meter box problem. Section 33-39 says the water meter box access cover must be exposed and not lower than finished grade, and Community Development "shall deny final approval and certificate of occupancy" until it is. A new asphalt or landscape grade that buries the lid can hold the certificate.

What should you do next?

  1. 1Ask the permit counter whether a temporary certificate is possible for your portion before you fall behind. The building official decides, based on safe occupancy.
  2. 2Request the final plumbing inspection from Building Safety and leave work exposed until approved (110.1). Inspection requests may be required at least one working day ahead (110.5).
  3. 3Confirm the meter box lid sits at finished grade before the final inspection.
  4. 4If the plans show a backflow assembly, see the backflow on plans page, because test results and the assembly need to be in place first.
  5. 5For a temporary certificate, pay the Table 2-A fee before it is issued and calendar the day it ends.
  6. 6Call Building Safety at 480-350-4311 with the permit number if a certificate is delayed.

What do people get wrong?

  • Reading temporary as open-ended. Each is limited to 30 days, with no more than three per permit.
  • Opening once plumbing passes. Tempe City Code 8-110.6 requires the final inspection and approval of all construction before any occupancy or use, and the certificate comes from the building official.
  • Moving in on a certificate of completion. The code says the letter of compliance does not authorize occupancy.
  • Believing a certificate cannot be taken back. Tempe City Code 8-111.4 allows revocation for errors, incorrect information or violations.

The city's code text governs; this page explains it.

How Do Other Valley Cities Handle It?

WhereWhat appliesSource
MesaMesa's Building Safety Director sets the time period for a temporary certificate and its conditions, and subsection (D) states no fixed length or count. Any use of a partially constructed building other than for construction needs prior approval.Mesa City Code 4-1-6(D)
Verified October 4, 2026
ScottsdaleA temporary certificate for a nonresidential building expires at the time stated, not to exceed 180 days, and power is de-energized at expiry. A cash deposit of all project permit fees or $2,500, whichever is greater, is required and is forfeited if the building is occupied without a valid certificate.Scottsdale City Code 31-9 (amending IBC 111.3)
Verified October 4, 2026

This page explains the rule. The official text at the source above governs.

Sources

Commercial Plumbing in Other Cities

More Tempe Codes and Permits

Related Rules and Questions

Questions About Tempe Plumbing Code?

We work to code every day across the Valley. Call the dispatcher and we'll tell you what your project needs.