How long does Scottsdale take to review a tenant improvement with plumbing?

Verified October 4, 2026
In Short

Scottsdale's Commercial Plan Review page lists 7 business days for administrative review and 10 business days for substantive review of a tenant improvement. Plumbing is part of the construction documents, so it rides that clock. Corrections send the plans back, and the process restarts when you resubmit.

Official Source
City of Scottsdale: Commercial Plan Review
Scottsdale Commercial Plan Review page, Plan Review Time Frames in Business Days
“Tenant Improvements | 7 days | 10 days”
Applies to:
Tenants, landlords, design professionals and contractors filing commercial tenant improvement plans in Scottsdale, including restaurant and medical build-outs with plumbing
Official fee:
Plan review fees are paid at application and additional fees before permit issuance, per Scottsdale's Planning and Development fee schedule
In force:
Scottsdale Commercial Plan Review page (last updated 2026-09-03); 2021 IBC, IPC and IgCC as adopted by Scottsdale
Last verified:
October 4, 2026, against the official page

Scottsdale publishes its plan review targets in business days, which makes a tenant improvement easier to schedule than in many cities. The catch is in one sentence further down the page: when plans come back for corrections, you "restart the process." A 17-day review can turn into two or three rounds if the plumbing sheets are thin.

What does Scottsdale's Commercial Plan Review page say?

The city's table, "Plan Review Time Frames in Business Days," gives tenant improvements 7 days of administrative review and 10 days of substantive review. The row reads "Tenant Improvements | 7 days | 10 days." For comparison on the same table:

  • XLT projects (commercial, multi-family, 50,000 square feet and up, 4 stories): 7 and 20 days.
  • All other plan types: 7 and 15 days.
  • Walls and signs: 5 and 5 days.

The page lays out five steps:

  1. 1Preliminary plan review meeting. For commercial projects, "a preliminary plan review meeting is advised."
  2. 2Submittal. Permit application options appear in Scottsdale SPUR after the Planning phase, "once entitlement or administrative approval is granted." The construction documents must show the work conforms to the adopted codes, "including International Green Construction Code IgCC."
  3. 3Administrative review. An address check and a check that the documents are complete and correctly formatted.
  4. 4Substantive review. Scottsdale reviews five disciplines: "Planning, Building, Engineering, Stormwater and Fire." If changes are required, the plans go back for corrections, and you "submit the amended plans and restart the process."
  5. 5Approval. Permit Services calculates fees and issues the permit after payment.

Fees are "paid at the time of application for plan review," and "Applications will not be processed until payment is received."

What do the key terms mean?

  • Tenant improvement (TI). Interior build-out or remodel of a commercial space for a tenant. Plumbing is often the largest trade on a restaurant or medical TI.
  • Administrative review. A completeness and format check, not a code review.
  • Substantive review. The code review itself, by discipline. The page does not list plumbing as its own discipline; plumbing sheets are part of the construction documents reviewed for code compliance. That is a reading of the page, not a city statement.
  • Business days. Weekdays the city is open. The table's numbers are the city's posted time frames.
  • Abandoned. An application with no good-faith progress 180 days after the last completed review.

Who does this cover?

Anyone filing commercial tenant improvement plans in Scottsdale: tenants, landlords, architects, engineers and contractors. Projects started before January 6, 2026 in the legacy eServices portal stay in that system until completed.

This does not apply to single-family remodels, which go through residential plan review, or to single-trade home work that only needs a Minimum Permit with no plan review.

Quick check: what affects your TI clock?

SituationEffect on timingWhy
Complete TI set, no correctionsAbout 7 + 10 business daysPosted time frames
Plumbing sheets missing a backflow assemblyCorrections, clock restartsSec. 49-68(a) requires assemblies on plans
Restaurant TI without grease interceptor detailsLikely correctionsInterceptor submittal items are separate
Fees not paid at applicationNot processedPage: not processed until payment
50,000 sq ft, 4-story building project7 + 20 daysXLT row, not the TI row
Approved plans, permit not pulled for 180 daysResubmit plans and pay plan review fees againPage: Extensions section

What does this look like in real life?

A coffee shop in a strip center. The architect holds a preliminary meeting, submits a full set with fixture schedules and the RP assembly shown on the domestic service, and pays the review fee in SPUR the same day. It clears in one round, inside the posted 7 and 10 days.

A dental office. The first submittal omits the backflow assembly detail. Sec. 49-68(a) says all backflow assemblies "shall be shown and specified on all required building and engineering plans." The set comes back, the designer adds it, and the review restarts.

The edge case. A restaurant tenant gets plans approved, then the lease stalls. Approval does not hold forever: "Failure to obtain a permit within 180 days of plan approval will require plans and payment of the appropriate plan review fees to be resubmitted," unless the building official grants a written extension first.

What should you do next?

  1. 1Book a commercial preliminary plan review meeting if the space has a kitchen, medical gas or a new restroom group.
  2. 2Put every backflow assembly on the plumbing sheets with its specification (Sec. 49-68(a)).
  3. 3For food service, assemble the grease interceptor submittal items before you file.
  4. 4Start the permit application in Scottsdale SPUR after the Planning phase approval and pay the plan review fee at submittal.
  5. 5Answer corrections in one complete resubmittal, since each one restarts the process.
  6. 6For administrative questions, call the One Stop Shop at 480-312-7725. The counter is at 7447 E. Indian School Road.

What do people get wrong?

  • Myth: 17 business days is a promise. It is the posted time frame per round. Corrections send the plans back and restart the process.
  • Myth: you can pay after review. Fees are due at application, and the page says applications will not be processed until payment is received.
  • Myth: approved plans stay approved. The permit must be obtained within 180 days of plan approval, or plans and plan review fees are resubmitted.
  • Myth: backflow can be added in the field. City approval of the intended installation is required before the building permit issues.

What happens if you skip it?

An application with no progress becomes "abandoned" 180 days after the last completed review, unless pursued in good faith or a permit has been issued. Building and backflow permits wait on approved plans, and Scottsdale requires the backflow test before a temporary certificate of occupancy.

How Do Other Valley Cities Handle It?

WhereWhat appliesSource
ChandlerChandler posts 20 working days for completeness review, 40 for substantive review and 60 overall for a commercial tenant improvement building permit. The 40 days are two substantive reviews of 20 working days each.Chandler Development Services Time Frames application supplement
Verified October 4, 2026
TempeTempe makes a permit application valid for one year from filing. Before it expires, an applicant may ask in writing for a one-time 180-day extension, with a renewal fee of 25 percent of the original plan review fee if plans are not yet approved, or 10 percent if they are approved but the permit has not been issued.Tempe City Code 8-105 (IBC 105.3.2 as amended)
Verified October 4, 2026

This page explains the rule. The official text at the source above governs.

Sources

Commercial Plumbing in Other Cities

More Scottsdale Codes and Permits

Related Rules and Questions

Questions About Scottsdale Plumbing Code?

We work to code every day across the Valley. Call the dispatcher and we'll tell you what your project needs.