Scottsdale wants a kitchen equipment list, a drawing that shows every drain, floor sink and vent, and interceptor size calculations on the city worksheet. Gravity interceptors also need site and civil drawings with setbacks and easements. A licensed plumbing contractor must do the work, and no interceptor may be installed at risk.
“All work shall be performed by a licensed plumbing contractor per ROC requirements.”
- Applies to:
- Restaurant owners, tenants, designers and licensed plumbing contractors installing or replacing a grease trap or interceptor in Scottsdale
- Official fee:
- Plan review and permit fees are on the City's Planning and Development fee schedules; not repeated here
- In force:
- 2021 IPC as amended by Scottsdale (Ord. 4550, Res. 12501); guidelines last modified 1/24/2023, since January 1, 2023
- Last verified:
- October 4, 2026, against the official page
The fastest way to lose weeks on a restaurant build in Scottsdale is to submit the interceptor late or half-drawn. The city's guidelines list what plan review wants, and the list is short enough to check before you upload.
What does Scottsdale require?
The guidelines carry ten minimum submittal requirements. In short:
- 1Plans may need to be prepared and stamped by an Arizona registrant.
- 2An interceptor cannot be installed "at risk", meaning before approval.
- 3The interceptor is single-user only.
- 4A list of all kitchen equipment.
- 5The location of kitchen equipment, floor drains, floor sinks and service sinks.
- 6Drain and vent sizes when possible.
- 7No dishwasher connected to a grease trap.
- 8Interceptor calculations under Ordinance 4550 and Resolution 12501, using the city's method.
- 9For a gravity interceptor, site plans and civil drawings, two copies of all documents, and all setbacks and public utility easements shown.
- 10All work by a licensed plumbing contractor under Registrar of Contractors requirements.
What do the key terms mean?
- At risk: the guidelines do not define the phrase. In permitting it generally means starting work before the city approves the plans, and the guidelines prohibit it for interceptors.
- Arizona registrant: an engineer or architect registered in Arizona. The guidelines say plans "may be required" to be stamped, so it depends on the job. The text does not list the triggers.
- Public utility easement (PUE): a strip of the property reserved for utilities. The guidelines ask gravity tank site plans to show every setback and PUE.
Who does this cover?
It covers owners and tenants who install or replace a grease trap or interceptor, and the design and plumbing team they hire. Under the city's guidelines an owner cannot do the work alone, because item 10 requires a licensed plumbing contractor. It also does not replace the city's other plan-review items for the rest of the tenant improvement.
Quick check: what does your project need?
| Project | What to submit | Why |
|---|---|---|
| New restaurant with a gravity interceptor | Equipment list, fixture and drain layout, worksheet, site and civil drawings, two copies | Items 4 to 9 |
| New restaurant with a hydromechanical trap | Equipment list, layout, worksheet | Site and civil drawings apply only to gravity units |
| Adding a dishwasher to a kitchen with a trap | Redesign to a gravity interceptor | Item 7, dishwashers cannot drain to a trap |
| Replacing a failed interceptor | Building permit through the One Stop Shop, plans showing the kitchen equipment and fixtures | Replacement guide |
| Owner installs a trap without a contractor | Not allowed | Item 10 requires a licensed plumbing contractor |
| Setting the tank before approval | Not allowed | Item 2, no installation at risk |
What does this look like in real life?
A new sushi bar in a shopping center. The designer produces an equipment layout and worksheet. Because the design needs a gravity tank, the civil sheets showing setbacks and easements go in the first submittal instead of arriving in a correction round.
An old restaurant that fails an inspection. The city's replacement guide says a violation must be fixed within the time on the inspection report, and the inspection form gives the option of 30 days for plan review and permits plus 60 days for installation. Those are form options, not code deadlines.
The edge case: the paper guide is old. The Grease Trap Replacement Guide is dated December 2013 and cites the 2012 IPC and code section 31-168. Scottsdale now uses the 2021 IPC amended by Section 31-85, so treat the guide as a process outline and the current guidelines as the rule.
What should you do next?
- 1Fill out the city's Grease Interceptor Size Determination Worksheet with the plumber. It is the last page of the guidelines PDF.
- 2Assemble the drawings: equipment list, fixture and drain layout, drain and vent sizes, and for gravity units the site and civil sheets.
- 3Use the current submittal process linked from Scottsdale's One Stop Shop; confirm whether the city requires digital documents or paper copies for your project.
- 4Wait for approval before ordering or setting the tank. After a permit is issued, projects started in the SPUR portal schedule inspections there.
- 5Ask the city's Industrial Pretreatment group about the guidelines, using the current contact information on the city website.
What do people get wrong?
- "We can set the tank and file the drawings after." Item 2 forbids at-risk installation.
- "A trap is fine for a small kitchen with a dish machine." Item 7 and IPC 1003.3.5.1 both say no.
- "The 2013 replacement guide is the current rule." It predates the 2021 IPC amendments and cites a section that has since been replaced.
This page summarizes the city's guidelines. The city's published guidelines and adopted code govern.
How Do Other Valley Cities Handle It?
| Where | What applies | Source |
|---|---|---|
| Phoenix | Every interceptor installed or replaced goes through plan review. A new interceptor cannot be submitted over the counter and goes through electronic plan review. Like-for-like replacement of a hydromechanical unit can be reviewed over the counter. | Phoenix FOG Best Management Practices Manual (June 2024), Installation and Replacement of Interceptors Verified October 4, 2026 |
| Mesa | Mesa's code sets the physical design: a 500 gallon minimum two-chamber tank, three chambers at 750 gallons or more, 18 inch downspouts, and a two-way cleanout within 5 feet before and after the tank. | Mesa City Code 8-4-22(E)(3) Verified October 4, 2026 |
This page explains the rule. The official text at the source above governs.
Commercial Plumbing in Other Cities
- ChandlerCan a Chandler business get an annual permit for repeat plumbing alterations?
- ChandlerHow long does a commercial tenant improvement permit take in Chandler?
- MesaWhat is Mesa's Annual Facilities Permit for plumbing work? City Code 4-1-4(F)
- MesaDo you need a certificate of occupancy to open or change a Mesa business? City Code 4-1-6
- MesaDo you need an industrial wastewater discharge permit in Mesa? City Code 8-4-16 and 8-4-18
- MesaDo you need a permit to connect a building to the Mesa sewer? City Code 8-4-8
More Scottsdale Codes and Permits
- Commercial PlumbingHow often must a Scottsdale car wash or repair shop pump its interceptor?
- Commercial PlumbingWhen does Scottsdale require a grease interceptor?
- Commercial PlumbingWhat size grease interceptor does Scottsdale require?
- Commercial PlumbingHow does Scottsdale inspect restaurant grease traps?
- Backflow PreventionHow often must a Scottsdale backflow assembly be tested, and by whom?
- Backflow PreventionWhich backflow assembly types does Scottsdale recognize, and how does it rate hazards?