A tenant improvement permit is required when work alters or repairs a building, when plumbing, electrical or HVAC systems are altered or expanded, or when occupancy changes. Plumbing plans are required when water or sewer lines are altered or the system is expanded, and show fixtures, isometrics, load calculations, gas, interceptors, backflow devices and water heater expansion tanks.
“Plumbing Plans: Required when water or sewer lines are altered, or the system is expanded.”
- Applies to:
- Tenants, owners, designers and plumbers doing commercial tenant improvement work inside the City of Maricopa
- Official fee:
- Fees are on the City of Maricopa Development Services fee schedule; the guide links to it and states no amounts
- In force:
- 2024 IPC adopted by Maricopa City Code 15.05.080 (Ord. 26-01), with local amendments; the guide itself lists 2018 codes (see body)
- Last verified:
- October 4, 2026, against the official page
Tenant improvement work in the City of Maricopa starts with a short guide from Development Services. It is easy to read and easy to misread, because one line in it says plumbing plans are required only in certain cases, and another puts the code edition in doubt.
What does the City of Maricopa guide say?
The City of Maricopa guide's Applicability section says: "A Tenant Improvement Building Permit is required under the following conditions." There are three:
- 1"When any work is done to enlarge, alter, repair, improve, convert, or cause the same to be done to any building."
- 2"When Electrical, Plumbing, Heating and Air Conditioning Systems are altered or expanded."
- 3A change of occupancy.
Before the permit issues, a Zoning Permit approval is needed to verify zoning compliance. Construction plans must be prepared, sealed, signed and dated by an Arizona registered design professional, and the guide says a registered professional is required per A.R.S. 32-141 unless exempt per A.R.S. 32-144.
The plumbing plan requirement is the quote above, followed by eight items:
- Show all existing and proposed plumbing fixtures.
- If any fixtures are added, provide waste and water isometrics.
- Provide water and waste calculations for added fixtures so existing services are shown to be adequate for the additional load.
- For gas appliances, provide a gas isometric with PSI, distances, BTU, demands and pipe sizes.
- Show locations and capacities of all grease, sand or oil interceptors.
- Specify all piping materials.
- Show all backflow prevention devices.
- Specify expansion tanks for all water heaters.
The city's submittal list also asks for water and septic "Will Serve" letters where applicable, and its site plan must show the water meter curb box and sewer tap locations.
What do the key terms mean?
- Altered or expanded. The guide does not define it. Adding a fixture is the case it names: the isometric and load calculation items apply "if any fixtures are to be added."
- Isometric. In drafting use, a piping diagram drawn in three dimensions; the guide does not define it. The guide asks for waste and water isometrics when fixtures are added, and a gas isometric for gas appliances.
- Change of occupancy. The guide lists it as its own trigger. A shift from retail to restaurant is a common example; the guide does not give examples.
Who does this cover?
Anyone doing tenant improvement work in a commercial space within the City of Maricopa. All food service facilities also need separate approval by Pinal County, and fire sprinkler and fire alarm submittals need their own permits and approvals.
This does not apply to work in unincorporated Pinal or Maricopa County, where the county issues permits.
One caution on codes. The guide, revised 9/2025, says the codes used are "2018 IBC, IMC, IEC, IFC & 2017 NEC" and names no plumbing code. The city's Building Safety page says Maricopa has adopted the 2024 edition of the International Building Codes, including the International Plumbing Code, with an effective date of February 2, 2026. Maricopa City Code 15.05.080 (Ord. 26-01) adopts the 2024 IPC with amendments, including "Delete Section 114.4 in its entirety" and "Amend Section 403.2 by changing the number 15 in Exception 2 to 30 and deleting Exception 3." Design to the 2024 IPC with those amendments, and ask Development Services before you rely on the guide's code list.
Quick check: does your job need the permit and plumbing plans?
| Situation | Tenant improvement permit? | Plumbing plans? |
|---|---|---|
| Moving a sink or adding a restroom fixture | Yes, plumbing altered or expanded | Yes, with isometrics and load calculations |
| Same fixtures, same locations, new finishes | Condition 1 (work to alter, repair or improve a building) may still apply; ask the city | Listed as required when water or sewer lines are altered or the system is expanded |
| Retail suite becomes a restaurant | Yes, change of occupancy | Yes if plumbing is altered; interceptor and backflow items apply |
| New gas appliance | Part of the plumbing plan set | Gas isometric with PSI, distances, BTU, demands and pipe sizes |
| New water heater in the suite | Plumbing plans apply if systems are altered or expanded | Specify an expansion tank for each water heater |
| Food service tenant | City permit plus separate Pinal County approval | Same plans, plus county review |
What does this look like in real life?
A dental office in a vacant suite. The tenant adds three operatories with sinks. Fixtures are added, so the plan set needs waste and water isometrics and the load calculation, and every new device on the water side, including backflow devices, shown. The designer seals the plans.
A cafe taking over a retail space. There is no plumbing change planned, but occupancy changes from retail to food service, which is its own trigger for the permit. The city also reminds food service tenants to get separate Pinal County approval, and the plan set shows interceptor locations and capacities if one is involved.
The edge case. A tenant says the work is "just a remodel" with no plumbing. The guide's first trigger covers work to alter, repair or improve a building. Whether a given scope is exempt is not stated in the guide, so Development Services has to answer that.
What should you do next?
- 1Get Zoning Permit approval first through the Planning and Zoning Division at 520-316-6920 or DSD@maricopa-az.gov.
- 2Have an Arizona registered design professional prepare and seal the plans.
- 3Build the plumbing plan set from the list above, and add the water and septic "Will Serve" letters where they apply.
- 4Apply through the city's VIP portal and pay fees from the Development Services fee schedule. The city's Rev 5/2026 turnaround chart lists Commercial Tenant review at 8 working days for a first review, 4 for later reviews, 20 for substantive review and 30 overall, and notes City Hall runs a four-day work week.
- 5Name files as (Plan Type) - (Project Name) - (Submittal #), PDF only.
- 6If the tenant is food service, start the Pinal County Environmental Health review in parallel.
What do people get wrong?
- Myth: The plumber's drawing is the plan. The guide requires plans prepared, sealed, signed and dated by an Arizona registered design professional, unless exempt per A.R.S. 32-144.
- Myth: Zoning comes later. Zoning Permit approval is a prerequisite before the TI permit issues.
- Myth: The guide's code list tells me the plumbing code. It names no plumbing code. The city's page and City Code 15.05.080 name the 2024 IPC.
- Myth: A city permit covers the restaurant. The guide says all food service facilities require separate approval by Pinal County.
How Do Other Valley Cities Handle It?
| Where | What applies | Source |
|---|---|---|
| Chandler | Chandler lists a commercial tenant improvement building permit at 20 working days for completeness review, 40 for substantive review and 60 overall, under A.R.S. 9-835 time frames. | Chandler Development Services Application Supplement: Time Frames Verified October 4, 2026 |
| Mesa | Mesa's plumbing plan checklist cites IPC 403.2 for separate toilet facilities for each sex, with a Mesa amendment for small occupancies of 25 or less. The City of Maricopa amends the same section 403.2 differently, by changing 15 to 30 in Exception 2 and deleting Exception 3. | City of Mesa Plumbing Plan Submittal Checklist (M-IPC 403.2) Verified October 4, 2026 |
This page explains the rule. The official text at the source above governs.
- City of Maricopa Development Services: Commercial Tenant Improvement Application Guide (Rev. 9/2025)
- City of Maricopa: Building Safety (adopted codes and effective date)
- Maricopa City Code 15.05.080: International Plumbing Code adopted, with amendments (Ord. 26-01)
- City of Maricopa Development Services: Plan Review Turnaround Times (Rev 5/2026)
Permits and Inspections in Other Cities
- ChandlerChandler plumbing inspections: the required list and inspection codes
- ChandlerDo you need a permit to repipe a house in Chandler?
- ChandlerHow do you schedule a plumbing inspection in Chandler?
- ChandlerWhat is the Chandler water meter worksheet when you add plumbing fixtures?
- ChandlerWhat happens if you do plumbing work without a permit in Chandler?
- GlendaleGlendale policy: tub and shower boxes must be grouted before the inspection
More Maricopa Codes and Permits
Related Rules and Questions
- Pinal CountyWhat plumbing details does Pinal County want in a restaurant plan review?
- MesaWhat does Mesa's commercial plumbing plan review checklist require?
- ChandlerHow long does a commercial tenant improvement permit take in Chandler?
- MesaCan a Mesa tenant improvement use permit-by-inspection? City Code 4-1-4(U)
- FAQWhat plumbing is involved in a commercial tenant improvement (TI)?
- FAQWhat should a tenant do about an old open plumbing permit before signing a lease?
- Commercial Plumbing
