Pinal County Environmental Health wants a plumbing schedule on every food establishment plan set, listing fixtures, sinks, floor drains and sinks, supply lines, overhead waste lines, water heating equipment with capacity and recovery rate, backflow devices and wastewater connections. Review runs within 30 business working days and approval expires one year after issuance.
“Plumbing schedule including location of all plumbing fixtures, sinks, floor drains, floor sinks, water supply lines, overhead waste-water lines, hot water generating equipment with capacity and recovery rate, backflow prevention devices, and wastewater line connections; etc.”
- Applies to:
- Restaurant owners, designers and plumbers building or remodeling a food establishment where Pinal County Environmental Health does the plan review
- Official fee:
- The packet says fees for plan review and the operating permit are paid at plan submission; it does not state amounts
- In force:
- Pinal County Food Establishment Plan Review Packet (undated; refers to the 2013 Food Code)
- Last verified:
- October 4, 2026, against the official page
Pinal County runs its own health plan review for restaurants, separate from Maricopa County's. Its packet is short, and the plumbing schedule is one line inside it that carries a lot of weight. Plans that are not approved go back with a request for additional information, so detail on that line matters.
What does the Pinal County packet say about plumbing?
The packet's "Contents and Format of Plans and Specifications" says plans should also include a plumbing schedule. The exact wording is the quote above. Under it the packet adds four more instructions:
- Clearly designate all food preparation sinks.
- Clearly designate "adequate hand-washing lavatories in the immediate area of food preparation and dishwashing, and for each restroom."
- Clearly designate a mop sink or curbed cleaning facility with facilities for hanging wet mops.
- Clearly designate the location of proposed or existing grease traps or interceptors, including type and size.
The plans also have to show the source of water supply and the method of sewage disposal, with evidence of compliance with state and local regulations. On drawing format, the packet asks for plans at least 8.5 x 11 inches at a minimum scale of 1/4 inch = 1 foot, or all dimensions shown if the plan is not to scale.
The process flow chart gives the order of events. The applicant gets a permit application and the packet online, at an office or by phone. The plan submission and meeting with Environmental Health Services follows, where fees for plan review and operating permit are paid. Review is "Within 30 business working days." If plans are not approved, additional information is requested. Plan approval "expires 1 year after issuance." The applicant then contacts Environmental Health Services for construction inspections "before final plumbing and after equipment installation," and for a preoperational inspection "at least 5 business days prior to operation."
What do the key terms mean?
- Plumbing schedule. The packet lists its contents but does not define the format. Treat it as a list or table on the plan set.
- Recovery rate. In general plumbing use, how fast water heating equipment heats water after use. The packet asks for it alongside capacity and gives no definition.
- Curbed cleaning facility. The packet's alternative to a mop sink. It does not describe the curb.
- Business working days. The packet's phrase for the review window. It does not define holidays. Its Appendix C separately says review time frames may be temporarily suspended (see the edge case below).
Who does this cover?
Food establishment projects where Pinal County Environmental Health is the plan reviewer, including food service tenants in the City of Maricopa, whose guide sends them to Pinal County.
This does not apply to projects in Maricopa County, which reviews restaurant plans under its own guide. The packet is also undated and cites the 2013 Food Code. Pinal County's own health code was not opened for this page, so confirm with Environmental Health that this is the current packet.
Quick check: what a Pinal County plan set should show
| Item | What the packet says to show | Notes |
|---|---|---|
| Fixtures and sinks | Location of all plumbing fixtures and sinks | Food prep sinks clearly designated |
| Hand sinks | Adequate hand-washing lavatories near food prep and dishwashing, and each restroom | No distance given |
| Mop sink | A mop sink or curbed cleaning facility with hanging space for wet mops | Show it on the plumbing schedule |
| Drains | Floor drains and floor sinks | Overhead waste-water lines also |
| Water heating | Hot water generating equipment with capacity and recovery rate | Maricopa County asks for size and type |
| Backflow | Backflow prevention devices | Type and location are on Appendix A |
| Grease | Grease traps or interceptors with type and size | Easily accessible and outside the building |
| Water and sewer | Source of water supply and method of sewage disposal | Evidence of compliance with state and local rules |
What does this look like in real life?
A new restaurant on a county road. The designer submits a scaled plan with the plumbing schedule, and the Environmental Health reviewer has everything needed. Approval is issued within the 30-business-day window.
A schedule that lacks recovery rate. The plan lists a water heater by size only. The packet asks for capacity and recovery rate, and its flow chart shows plans that are not approved going back with a request for more information. Putting both numbers in the first submittal avoids that.
The edge case. An owner gets approval, then loses a year to a lease dispute. The flow chart says plan approval expires 1 year after issuance, so construction that has not started needs fresh approval. The packet does not say whether the one-year clock can be extended.
A review that stalls on a request for more information. Appendix C of the packet, "Licensing Time Frames," says that under A.R.S. 11-1605 review time frames "may be temporarily suspended" for public hearings, for state or federal approvals, and "to wait for the applicant to submit additional information as requested by Pinal County." It also says time frames "include Pinal County's review time and not the time the applicant takes responding to notices of deficiencies," and that "Applications that have been inactive for more than one year since the date of a suspension notice will be administratively closed." So the 30-business-day window runs while the county reviews, not while the packet waits on you, and an application left unanswered for a year after a suspension notice is closed and has to be started over. Appendix C also carries a separate table of licensing time frames in calendar days for the permit application, which does not match the flow chart's 30 business days, so ask Environmental Health which clock applies to your plan review.
What should you do next?
- 1Request the permit application and packet from Pinal County Environmental Health online, at the office or by phone. The packet lists 971 Jason Lopez Cir., Bldg D, Florence, AZ 85132, phone 520-866-6864.
- 2Build the plan set: scaled floor plan, site plan, proposed menu, seating capacity, food equipment schedule, and the plumbing schedule with every item listed above.
- 3Attach the permit application and the Plan Submittal Checklist (Appendix A) with the plan submittal.
- 4Meet with Environmental Health Services and pay the plan review and operating permit fees at submission.
- 5Request a construction inspection before final plumbing and after equipment installation, then a preoperational inspection at least 5 business days before operating.
What do people get wrong?
- Myth: Maricopa County's rules apply to every Arizona restaurant nearby. Pinal County is a separate reviewer with its own packet.
- Myth: The plumbing schedule can wait until rough-in. The packet asks for it as part of the plans, and inspections are tied to final plumbing.
- Myth: A plan approval is good indefinitely. The packet says approval expires 1 year after issuance.
- Myth: A city permit covers the health review. The City of Maricopa's guide says all food service facilities will require separate approval by Pinal County.
How Do Other Valley Cities Handle It?
| Where | What applies | Source |
|---|---|---|
| Maricopa County | Maricopa County's plumbing schedule names the location, size and type of water heaters, overhead wastewater lines, floor drains and floor sinks, wastewater line connections and backflow devices. The county guide recommends applying 6 to 8 weeks before construction and describes three inspections: rough plumbing, equipment, and final. | Maricopa County Environmental Services Plan Review Construction Guide (Rev 09/04/2026) Verified October 4, 2026 |
| Maricopa | The City of Maricopa, which sits in Pinal County, says all food service facilities will require separate approval by Pinal County and lists the Division of Environmental Health in Florence, phone (520) 866-6864. | City of Maricopa Commercial Tenant Improvement Application Guide (Rev. 9/2025) Verified October 4, 2026 |
This page explains the rule. The official text at the source above governs.
Commercial Plumbing in Other Cities
- ChandlerCan a Chandler business get an annual permit for repeat plumbing alterations?
- ChandlerHow long does a commercial tenant improvement permit take in Chandler?
- GilbertDoes your Gilbert business need a Class A or Class B wastewater discharge permit?
- Maricopa CountyDoes a restaurant remodel need Maricopa County plan approval, and what plumbing goes on the plans?
- MesaWhat is Mesa's Annual Facilities Permit for plumbing work? City Code 4-1-4(F)
- MesaDo you need a certificate of occupancy to open or change a Mesa business? City Code 4-1-6
More Pinal County Codes and Permits
Related Rules and Questions
- MaricopaDoes a City of Maricopa restaurant need Pinal County approval?
- MaricopaWhen does a City of Maricopa tenant improvement need a permit, and what plumbing plans go with it?