Plumbing rough-in inspection checklist: what Cave Creek inspectors check

Verified November 12, 2026
In Short

Before walls are closed, Cave Creek's inspector wants the drain, waste and vent piping to hold a 10 foot water test for 15 minutes and the water lines to hold working pressure or 50 psi for 15 minutes. Plastic drain pipe may not be air tested. Traps, vents, cleanouts and supports must match the Town's checklist.

Official Source
Town of Cave Creek: Inspection checklist, Plumbing Rough Trade (PDF)
Town of Cave Creek Plumbing Rough Trade inspection checklist; Town Code Chapter 151 (Ordinance 2025-08), IPC 105.4.3 as amended
“Drains, waste and vents (DWV) water tested with a 10' head for 15 minutes or air tested at 5 psi for 15 minutes. Plastic DWV not allowed to be tested with air.”
Applies to:
Homeowners, owner-builders and plumbing contractors with a plumbing permit for a new home, addition or remodel inside the Town of Cave Creek
Official fee:
Inspections are part of the plumbing permit; permit fees follow Town Code 151.14 and the Town's Comprehensive Fee Schedule, and a permit restarted after it expires costs one half of a new permit
In force:
Town checklist written against the 2021 IRC; the Town adopted the 2024 International codes as amended by Ordinance 2025-08 for permit applications from January 1, 2026, since January 1, 2026
Last verified:
November 12, 2026, against the official page

A plumbing rough-in inspection in Cave Creek is a test and a look before anything is covered. The inspector wants the drain, waste and vent piping filled with water to a 10 foot head for 15 minutes, the water lines held at working pressure or 50 psi for 15 minutes, and every trap, vent, cleanout, hanger and nail plate where the Town's checklist puts it. Plastic drain pipe may not be tested with air. The permit and the approved plans have to be on the job.

What does a rough-in inspection include in Cave Creek?

The Town publishes a Plumbing Rough Trade checklist on its Building and Fire Code Compliance page, beside separate checklists for under slab plumbing, fuel gas piping and the plumbing final. It is a list to prepare from, written against the 2021 International Residential Code, and the Town now enforces the 2024 codes as amended by Ordinance 2025-08. The lines that fail the most jobs are the tests:

  • Drains, waste and vents. "Water tested with a 10' head for 15 minutes or air tested at 5 psi for 15 minutes. Plastic DWV not allowed to be tested with air."
  • Water lines. "Tested to working pressure or 50 psi for 15 minutes." Plastic water pipe may not be air tested either, except PEX where its maker calls for an air test.
  • CPVC under a slab. A pressure test of 150 psi for two hours.

The rest of the list covers how the pipe is run: no pipe embedded in concrete, Type L copper under ground with brazed joints under a slab, wrapped steel, 18 gauge nail plates where pipe sits within 1 inch of the face of a stud, and plastic pipe supported every 4 feet.

What do the key terms mean?

  • Rough-in. The pipes inside walls, floors and ceilings, set before drywall and fixtures. Our guide to what plumbing rough-in is walks through the stages.
  • 10 foot head. The drain system is plugged and filled with water to 10 feet above the work being tested, and the level must not drop.
  • Trap arm. The pipe from a fixture's trap to its vent. Too long and the trap can siphon dry.
  • Cleanout. A capped opening that lets a drain be cleared without cutting pipe.

Why does the no air test rule matter?

Air is compressible. If a glued plastic joint lets go under air pressure, the stored energy can throw pipe and fittings with real force, and a crew may not see it coming inside a wall. Water does not store that energy, and a leak shows as a wet joint and a falling level. The Town's checklist allows an air test only on drain pipe that is not plastic, so PVC and ABS get water. Plan the water source, test plugs and a way to drain the system before calling for the inspection.

What is the 135 rule in plumbing?

It is a cleanout rule, and Cave Creek's checklist states it twice. A cleanout is required at each horizontal change of direction that adds up to more than 135 degrees. A trap arm 3 inches or larger cannot change direction more than 135 degrees without one, and a trap arm under 3 inches cannot turn more than 90 degrees without one. Each horizontal drain also needs a cleanout at its upper end and one for every 100 feet of run.

Who does this cover?

Anyone with a plumbing permit inside the Town of Cave Creek: owners building a custom home, owner-builders adding a casita or a bath, remodelers opening walls, and the licensed plumbers they hire. The same checklist applies whether the house is on Town sewer or a septic tank, since the rough-in is the piping inside the building. A lot outside the Town limits gets its permits and inspections from Maricopa County instead, even with a Cave Creek mailing address.

Quick check: will this rough-in pass?

ItemWhat the Town's checklist asks for
Drain, waste and vent test10 foot water head for 15 minutes; air at 5 psi only on non-plastic pipe
Water line testWorking pressure or 50 psi for 15 minutes
Trap arm length2 feet 6 inches for 1 1/4 inch pipe, 3 feet 6 inches for 1 1/2 inch, 5 feet for 2 inch, 6 feet for 3 inch, 10 feet for 4 inch and larger
Toilet to its ventNo more than 6 feet
Vent rise6 inches above the fixture's flood rim before it turns horizontal
Vent at the roof6 inches above the roof, and 3 feet above or 10 feet from a window that opens
Air admittance valve4 inches above the drain, 6 inches above attic insulation, accessible
Cleanout clearance12 inches for pipe 2 inches and smaller, 18 inches for larger pipe
Laundry standpipe18 to 30 inches above its trap, trap 6 to 18 inches above the floor
Water service3/4 inch minimum, a pressure reducing valve over 80 psi, blue 18 gauge tracer wire from the meter to the foundation

What does this look like in real life?

A bathroom remodel. The walls are open, the new shower valve is in and the drain is PVC. The plumber caps the drain, fills the stack to 10 feet and leaves it for the inspector. The checklist also asks for a listed anti scald valve set to 120 degrees at most and a shower at least 30 inches across.

A new custom home on a desert lot. The under slab plumbing was inspected first. At rough-in the inspector looks at the trap arm lengths, the vents through the roof and the water service. Where a metal water service is replaced with plastic, 10 feet of copper stays in the ground on the house side to keep the electrical ground, or the Building Official approves another way.

The edge case. A crew air tests a PVC drain to save time. The Town's checklist does not allow that test on plastic, so plan on filling the drains with water before the inspector arrives.

What should you do next?

  1. 1Pull the plumbing permit and keep it with the approved plans on site, with the job address posted where it can be seen.
  2. 2Finish the rough-in before you call: every fixture drain, vent and supply in place, plates on the studs, supports at 4 feet.
  3. 3Set up the tests: water to a 10 foot head on the drains and 50 psi or working pressure on the water lines, held for 15 minutes.
  4. 4Book the inspection through the Town's online permitting and inspection portal, and keep the walls open until it passes.
  5. 5Keep the job moving. Under Ordinance 2025-08 a permit expires if the work does not pass an inspection within 180 days of the permit, or stops passing inspections for 180 days, and restarting it costs one half of a new permit.

HQ Plumbing & Air serves homes in Cave Creek. See residential plumbing or our Cave Creek service area page. The next stage is the Cave Creek plumbing final inspection.

What do people get wrong?

  • "An air test is faster, so it is fine." Not on plastic drain pipe in Cave Creek. Use water.
  • "The under slab inspection covered it." The Town keeps under slab, rough and final as separate checklists, each with its own items.
  • "The inspector will tell me what is missing." The checklist is public. A failed rough-in means a second visit and a wall that stays open longer.
  • "Cave Creek works like Phoenix." Phoenix puts the stages in its code. Cave Creek adds its own checklist on top, with test methods spelled out.

How Do Other Valley Cities Handle It?

WhereWhat appliesSource
PhoenixPhoenix writes the stage rule into its code rather than a checklist: a rough-in or underground inspection is required for all sewer, drainage, vent, water and gas piping before it is buried or concealed, and tests follow the plumbing code.Phoenix Building Construction Code, IBC Chapter 1 Section 110.3.10.1, item 3
Verified October 4, 2026
ChandlerChandler's homeowner manual calls for the rough plumbing inspection when all rough-in plumbing is installed and under pressure test but not covered, with groundwork, water service and building sewer as separate stages.Chandler Homeowner Building Permit Manual, List of Required Inspections
Verified September 29, 2026

This page explains the rule. The official text at the source above governs.

Sources
Talk to a plumber

Need this done to Cave Creek code?

We pull the permit when the job needs one and do the work to the code on this page. For restaurants, offices and rental properties, we schedule it around your hours.

  • 24/7 emergency service
  • Licensed and insured
  • Upfront pricing
  • Free estimates
See Residential Plumbing

Permits and Inspections in Other Cities

More Cave Creek Codes and Permits

Related Rules and Questions

Questions About Cave Creek Plumbing Code?

We work to code every day across the Valley. Call the dispatcher and we'll tell you what your project needs.