Mesa reviews commercial plumbing plans against a nine-page checklist built on the 2024 IPC with Mesa amendments. It covers fixture counts, water service, drainage, vents, backflow, roof drains and interceptors. Plumbing systems cannot be deferred to a later submittal, and incomplete packages can be returned without review.
“Water meter, water service, sewer, storm drainage pipe sizes and locations on civil sheets shall match plumbing plans.”
- Applies to:
- Plumbing designers, engineers, general contractors and tenants preparing commercial plumbing drawings for Mesa plan review
- In force:
- Mesa Plumbing Plan Submittal Checklist (2024 IPC with Mesa amendments); Mesa City Code Title 4, Chapter 1
- Last verified:
- September 29, 2026, against the official page
Plan review is where a commercial plumbing job stalls or moves. Mesa publishes the list its reviewers work from, and the items are specific enough that a drawing set can be checked against it before submitting. This page walks through what the checklist covers and where the city's own numbers do not quite line up.
What does the Mesa plumbing plan checklist cover?
The nine-page checklist says its references follow the 2024 International Plumbing Code, building, residential, fuel gas, fire, energy and mechanical codes, the Mesa Administrative Code and NFPA standards, with Mesa amendments marked "M". IPC Sections 101.4 through 115.4 are deleted, and administrative rules come from Mesa City Code Title 4, Chapter 1. The 2024 IPC Appendices C and E are adopted. Its sections run as follows:
- Administrative and general. A project narrative, site address, vicinity map and site plan. Sealed sheets need a legible seal with the registrant's license number and signature date.
- Plumbing facilities. Occupant load or minimum fixtures under IPC Table 403.1, separate toilet facilities for each sex with an exception for small occupancies of 25 or less, an accessible family or assisted-use toilet in assembly and mercantile occupancies with six or more water closets, toilet access that does not pass through a kitchen, storage or closet, and drinking fountains within 500 feet, with an exception for occupant loads of 50 or less. Service sinks are not required in Groups B and M where the occupant load does not exceed 100 persons (Mesa amendment to IPC 403.1).
- Low-flow fixtures. Flow rates must meet the Mesa version of IPC Table 604.4. Underground nonmetallic water pipe of 2 inches or more needs insulated copper tracer wire or an approved conductor, 14 AWG minimum.
- Civil and site plan. Water meter, service, sewer and storm drainage sizes and locations on the civil sheets must match the plumbing plans, and required grease or sand-oil interceptors and their locations must be shown.
- Water service and distribution. Specialty fixtures limited to 120°F, tempered water 85° to 120°F at hand sinks, emergency showers and eyewash stations, water heater 18 inches above an ignition source, a safe pan and drain line, a temperature and pressure relief line termination, sizing calculations, a pressure reducing valve above 80 psi, recirculation or insulated hot water lines no longer than 50 feet, insulation, thermal expansion control and combustion air.
- Drainage and vents. Trap and drain sizing, slopes, cleanouts, three-compartment sinks and independent waste receptors in food handling, oil separators at repair garages, car washes and factories with oily waste, hydraulic elevator pits (with an exception if an approved alarm system is installed), interceptors and pipe material identification, plus vent sizing and terminations.
- Backflow prevention. Protection at potential cross connections, kitchen equipment, carbonators, medical equipment and dental vacuum pumps. The list states that "Backflow devices shall be reviewed and approved before installation" and points to the city backflow group. See 8-1-6.
- Roof drainage. Sizing calculations, scupper dimensions, separate endpoints for primary and secondary drains, and no drainage over public walking surfaces.
- Interceptors. Grease interceptors reviewed and approved before installation, through Industrial Pretreatment. See 8-4-22.
The checklist ends with worked samples for fixture counts and roof drain sizing.
What does the city code add about submittals?
Under Mesa City Code 4-1-4(I), plans and calculations go in with each application, prepared by a registered design professional as state law requires. Submittals are screened for completeness and code compliance before acceptance, and incomplete ones, or ones with readily apparent code violations, can be returned. Deferred submittals are allowed for items such as fire sprinklers, kitchen hoods and elevators, but the code lists "building plumbing systems" among the items that shall not be deferred.
What do the key terms mean?
- M-IPC. The 2024 International Plumbing Code as amended by Mesa.
- Screening. The intake check that decides whether a submittal is complete enough to review.
- Deferred submittal. A portion of the design filed after the application with the director's prior approval. Building plumbing systems are not eligible.
- Civil sheets. The site and utility drawings that show meter, water service, sewer and storm drain.
Who does this cover?
Design professionals and contractors preparing plumbing drawings for a commercial permit in Mesa, including tenant improvements. Restaurant, medical and industrial tenants hit more of the list, because of interceptors, medical gas and vacuum, and cross connections.
Quick check: where do submittals commonly need attention?
| If your project has | Checklist item | Note |
|---|---|---|
| Any public restroom | Fixture count and ratios | Worked sample at the end of the checklist |
| A kitchen or food handling | Three-compartment sink, grease interceptor, backflow at kitchen equipment | Interceptor and backflow approved before installation |
| A repair garage, car wash or elevator pit | Oil separator | Elevator pit has an alarm exception |
| A new or changed water service | Sizes on civil sheets match plumbing plans | Meter, service, sewer and storm pipe sizes and locations |
| A water heater | Height above ignition source, safe pan, T&P line, expansion control | Water Service section |
| Deferred items | Plumbing cannot be deferred | 4-1-4(I)5 |
What does this look like in real life?
A restaurant tenant improvement. The set shows the three-compartment sink, the grease interceptor and its location on the civil sheet, and a backflow assembly at the carbonator. Each of those is a checklist line, so the reviewer finds it where expected.
An office remodel. A new restroom cluster is sized from the occupant load. Under the checklist, occupancies of 25 or less can skip separate facilities by sex.
The edge case. The checklist's own sample treats service sinks differently from the amendment line. The text says service sinks are not required for Groups B and M when the occupant load is 100 or less, while the sample note refers to an occupant load of 15 or fewer. Check with a plans examiner which reading applies to a borderline occupant load.
What should you do next?
- 1Work through the checklist section by section against your drawing set before submitting.
- 2Make sure the civil sheets match the plumbing plans for meter, service, sewer and storm drain.
- 3Show interceptor and backflow assemblies on the plans, since both must be approved before installation.
- 4Do not plan to defer plumbing to a later submittal.
- 5Have the design professional's seal, license number and signature date legible on every sealed sheet.
What do people get wrong?
- "Plumbing can be a deferred submittal." The code says building plumbing systems shall not be deferred.
- "The civil set and the plumbing set are separate." The checklist requires the sizes and locations to match.
- "The interceptor can be sorted out at inspection." It has to be reviewed and approved before installation.
- "The checklist is the whole code." It is a review aid built on the 2024 IPC with Mesa amendments.
How Do Other Valley Cities Handle It?
| Where | What applies | Source |
|---|---|---|
| Phoenix | Phoenix requires a commercial building permit with plan review for non-residential remodels, tenant improvements and changes of use, submitted through the SHAPE PHX portal. Moving or adding fixtures counts as plumbing work needing review. | City of Phoenix Planning and Development, Commercial and Multifamily Building Verified September 29, 2026 |
| Chandler | Chandler posts review time frames for a commercial tenant improvement building permit: 20 working days for the completeness review, 40 for substantive review and 60 working days overall, with the clock stopped while you answer a deficiency notice. | Chandler Development Services Time Frames (A.R.S. 9-835) Verified September 29, 2026 |
This page explains the rule. The official text at the source above governs.
Commercial Plumbing in Other Cities
- ChandlerDoes a Chandler restaurant need a grease trap or interceptor?
- ChandlerCan a food truck dump wastewater at a Chandler commissary?
- ChandlerChandler sewer discharge limits for businesses: FOG, pH and surcharges
- PhoenixWho approves a fire line connection in Phoenix?
- PhoenixPhoenix restaurants: When do you need an outdoor gravity grease interceptor instead of a grease trap?
- TempeTempe FOG inspections: pumping schedule, records and what inspectors check
More Mesa Codes and Permits
- Commercial PlumbingWhat is Mesa's Annual Facilities Permit for plumbing work? City Code 4-1-4(F)
- Commercial PlumbingCan a Mesa tenant improvement use permit-by-inspection? City Code 4-1-4(U)
- Commercial PlumbingDo you need a certificate of occupancy to open or change a Mesa business? City Code 4-1-6
- Commercial PlumbingMesa water and sewer capacity fees for a commercial project: City Code 8-10-13 and 5-17-5
- Commercial PlumbingWhat can a Mesa business not put down the drain? City Code 8-4-15 prohibited discharges and limits
- Commercial PlumbingDo you need an industrial wastewater discharge permit in Mesa? City Code 8-4-16 and 8-4-18
Related Rules and Questions
- MesaMesa backflow assemblies on building plans, and new inspections when you add equipment: City Code 8-1-6 and 8-1-7
- MesaMesa City Code 8-4-22: who needs a grease interceptor and what upkeep it takes
- MesaWhen do you need a plumbing permit in Mesa, and what is exempt? City Code 4-1-4
- ChandlerHow long does a commercial tenant improvement permit take in Chandler?
- FAQWhat plumbing does Maricopa County review in restaurants?
- Commercial Plumbing