Surprise Permit Fee

How much does the City of Surprise charge to install a water meter?

Verified October 4, 2026
In Short

The Surprise Citywide Fee Schedule (Resolution 2026-16, effective 5/19/2026) lists water meter installation per meter by size, from $422.70 for a 3/4 inch ultrasonic meter to $19,050.00 for 8 inch. It says the fee is the listed market cost, updated yearly on July 1st. Except single-family homes and duplexes, each user needs a separate irrigation meter.

Official Source
City of Surprise Citywide Fee Schedule (Resolution 2026-16, effective 5/19/2026)
Surprise Citywide Fee Schedule, Resolution 2026-16
“Water Meter Installation - Fee amount is the listed market cost updated yearly on July 1st”
Applies to:
Builders, owners and contractors setting new water service in Surprise, and commercial and multifamily owners who need separate domestic and irrigation meters
Official fee:
Surprise Citywide Fee Schedule (Res. 2026-16, effective 5/19/2026): 3/4 inch $422.70; 1 inch $428.20; 1.5 inch $916.13; 2 inch $1,138.08; 3 inch $3,238.00; 4 inch $4,145.00; 6 inch $6,653.00; 8 inch $19,050.00, each per meter
In force:
Surprise Municipal Code Ch. 58, Art. I (Ord. 2012-06) and Citywide Fee Schedule, Res. 2026-16, since May 19, 2026
Last verified:
October 4, 2026, against the official page

Chandler and El Mirage publish fixed meter tables. Surprise's schedule says the fee is "the listed market cost," updated each July 1. So the table is a snapshot, and the date on it matters more than usual.

What does the Surprise fee schedule say?

The Citywide Fee Schedule, Resolution 2026-16, effective 5/19/2026, carries this heading in the Water Resource Management section: "Water Meter Installation - Fee amount is the listed market cost updated yearly on July 1st." The amounts below it, each "Per Meter," are ultrasonic meters:

Meter sizeFee per meter
3/4 inch$422.70
1 inch$428.20
1.5 inch$916.13
2 inch$1,138.08
3 inch$3,238.00
4 inch$4,145.00
6 inch$6,653.00
8 inch$19,050.00

The schedule does not say whether the figure includes labor, a tap, a meter box or a trench. It lists only the meter. The city's Permits and Applications page linked this same schedule on 2026-10-04, so it was the current posted version that day. The July 1 clause means the next posted version may differ.

What do the key terms mean?

  • Market cost: the schedule's own phrase. It does not define it or say how the city sets it.
  • Ultrasonic meter: the meter type the schedule prices. It does not say whether the city will accept another type.
  • Separate meter for each account or use: Section 58-6(c) says "Each utility user shall have a separate meter for each account or use, as applicable."

Who does this cover?

Anyone setting a water meter on the Surprise system. The schedule does not say who pays or when, so ask the city. The meter belongs to the city: 58-5(a) says "Title to the meters installed shall remain in the city and said meters shall be serviced and repaired by the city." Repair costs fall on the city "except in the instance of tampering or otherwise damaging a meter," when the city may bill the customer.

Quick check: how many meters, and which fees?

SituationMetersWhy
Single-family home or duplexOne meter per account or use; no separate irrigation meter required58-6(d) excepts single-family and duplex units
Retail center, office or restaurant with landscapingDomestic meter plus separate irrigation meter58-6(d)
Apartment complexDomestic meter or meters plus separate irrigation meter58-6(c) and (d)
Two businesses in one building with separate accountsA separate meter for each account58-6(c)
Non-residential user on city sewer with water from another providerCity may require a sub-meter on non-irrigation services58-6(e)
Service size in an applicable schedule is not adequate for the intended useCity may require a larger meter and service58-6(b)

What does this look like in real life?

A small restaurant in a new plaza. The space needs a domestic meter, and the plaza's landscaping needs its own irrigation meter. Two meters means two lines on the fee schedule, at the sizes the engineer picks.

A fourplex. A fourplex is not a duplex. The irrigation meter exemption in 58-6(d) names only single-family and duplex units, so the landscaping needs its own meter.

The edge case: the July 1 update. A builder budgets from a table dated 5/19/2026 and pays in the fall. The schedule says the amounts are updated yearly on July 1st, so confirm the figure for the day you pay.

What should you do next?

  1. 1Have the engineer size the service from the fixture count. The city can require a larger meter than a schedule shows if documentation shows it is not adequate (58-6(b)).
  2. 2Decide how many meters you need: one per account or use, plus irrigation unless the property is a single-family home or duplex.
  3. 3Pull the current Citywide Fee Schedule from the Permits and Applications page and check the date and the Water Resource Management section.
  4. 4Call Water Resource Management at 623-222-6000 to confirm the amount that applies to your meter size and when it is due.
  5. 5Plan the customer-side piping. Section 58-10 puts the customer in charge of facilities "from the customer side of the meter."

What do people get wrong?

  • Copying a fee from an old schedule. This one is tied to a yearly July 1 update.
  • Assuming one meter covers everything. Anyone other than a single-family home or duplex needs a separate irrigation meter.
  • Assuming the meter is the customer's property. Title stays with the city.
  • Comparing it to another city's table without checking what is included. Chandler's code gives two different fees depending on who installs the service line and meter box.

Full text and source

The amounts are from the Surprise Citywide Fee Schedule, Resolution 2026-16, and the metering rules are Sections 58-5, 58-6 and 58-10 of the Municipal Code. This is an explanation, and the posted schedule and code govern.

How Do Other Valley Cities Handle It?

WhereWhat appliesSource
ChandlerChandler's code lists a fee where the city installs the service line and meter box ($1,819.00 for 3/4 inch inside the city) and a lower fee for meter installation where a developer installs the line and box ($419.00 for 3/4 inch).Chandler City Code 50-9.1 and 50-9.2
Verified October 4, 2026
El MirageEl Mirage's FY26-27 schedule lists meters by size, from $450 for 5/8 inch to $17,000 for 12 inch, with a hydrant meter at $2,500. The schedule lists a fixed amount for each size.El Mirage Adopted Fee Schedule FY26-27, Water Meters
Verified October 4, 2026

This page explains the rule. The official text at the source above governs.

Sources

Water Supply and Pipes in Other Cities

More Surprise Codes and Permits

Related Rules and Questions

Questions About Surprise Plumbing Code?

We work to code every day across the Valley. Call the dispatcher and we'll tell you what your project needs.