Chandler sets non-residential water, wastewater and reclaimed water development fees by water meter size in Chapter 38, Appendix A, Table A. A 3/4 inch disc meter is $3,690 for water and $8,984 for wastewater. A 2 inch disc or turbine meter is $19,680 and $47,912. The fees are paid when the building permit is issued.
“system development fees shall be paid at the time of issuance of a building permit according to the current system development fee schedule for the applicable service area(s)”
- Applies to:
- Owners, developers and tenants adding, upsizing or changing the water meter on a non-residential Chandler property
- Official fee:
- Chandler City Code Chapter 38, Appendix A, Table A (Ord. 5083, effective July 1, 2024): by meter size, water and wastewater
- In force:
- Chandler City Code Chapter 38, Appendix A (Ord. 5083, adopted April 4, 2024, effective July 1, 2024), since July 1, 2024
- Last verified:
- October 4, 2026, against the official page
The line item that surprises commercial owners in Chandler is not the plumbing permit. It is the utility system development fee, and it is driven by one number: the size of the water meter.
What does Chandler's Table A say?
Chapter 38 of the city code sets system development fees, and Appendix A holds the schedule. "Table A: Non-Residential Utility System Development Fees" lists three utility fees for each meter size and type: reclaimed water, wastewater and water. The version on Municode was adopted by Ordinance 5083 on April 4, 2024, and the ordinance's editor's note says the amended fees became effective July 1, 2024. The city's own PDF of the schedule is titled with the same July 1, 2024 date.
| Meter | Reclaimed water | Wastewater | Water |
|---|---|---|---|
| 3/4 inch disc | $1,641 | $8,984 | $3,690 |
| 1 inch disc | $2,735 | $14,973 | $6,150 |
| 1 1/2 inch disc | $5,470 | $29,945 | $12,300 |
| 2 inch disc or turbine | $8,752 | $47,912 | $19,680 |
| 4 inch compound | $27,350 | $149,725 | $61,500 |
The table continues through 8 inch meters. For meters 10 inches and larger, the fee is the 1 inch fee multiplied by the meter's safe maximum operating capacity in gallons per minute divided by 20. Footnote 1 says there are no reclaimed water or wastewater fees for water-only (landscape) connections.
What do the key terms mean?
- System development fee: a fee on development that Chapter 38 sets under A.R.S. 9-463.05, Arizona's development fee statute.
- Meter size: under 38-11(A)(1)(c), the actual meter size installed on the lot. If the exact size is not in the table, the city uses the next largest. Where a lot has separate meters, the fees are added up.
- Water-only (landscape) connection: the table's phrase for a landscape connection that receives water only. The code does not define it further.
- Reclaimed water column: a separate fee, which this page reads as applying to a reclaimed water connection. The table does not say so in words.
Who does this cover?
It covers new development and changes that add demand: a new building, a new or larger meter, a change of use. It does not cover several situations the code names. Under 38-11(B), fees are not owed where they were already paid and the permit has not expired, where an existing building is modified without adding units of demand, increasing its impact or moving to a higher-fee category, or for meters dedicated only to fire flow. The wastewater fee also skips separate meters installed only for irrigation.
Quick check: what do you owe?
| Situation | Outcome | Why |
|---|---|---|
| New building with a 2 inch meter | $19,680 water and $47,912 wastewater | Table A |
| New irrigation-only meter | No wastewater or reclaimed fee | Table A footnote 1 and 38-11(B)(4) |
| Meter dedicated only to fire flow | No water, wastewater or reclaimed fee | 38-11(B)(4) |
| Meter upsized on a lot with a valid certificate of occupancy | New fees minus the fees for the previous development | 38-11(A)(1)(e) |
| Remodel that adds no demand | No fee owed | 38-11(B)(2) |
| Permit expired or voided and renewed by the original permittee | Pays the difference from the fees paid | 38-11(A)(6)(a) |
| Same permit sought by someone else | Pays the full current fees | 38-11(A)(6)(b) |
| Fee not paid | No building permit, water or sewer connection or certificate of occupancy issues | 38-11(A)(4) |
What does this look like in real life?
A new retail building. The plumber sizes the domestic meter at 2 inches. The water and wastewater fees on that meter size come due when the building permit is issued.
A tenant improvement that needs a bigger meter. An existing building with a certificate of occupancy upsizes its meter. The charge is the new schedule's fees for the proposed development minus the fees for the previous one, and if the result is negative no refund is given.
The edge case: the fire meter. A building needs a larger meter for fire flow after a change of use. Under 38-11(B)(4), the fee is based only on the meter size upgrade required for domestic consumption. A meter used only for fire flow carries none of the three utility fees.
The 24-month lock. For non-residential development, the fee schedule in force at final site plan approval stays in force for 24 months from that approval. If the city lowers a fee in that window, the lower fee applies.
What should you do next?
- 1Get the domestic and fire demand sized before you submit, because the meter size drives all three fees.
- 2Find your meter's row in Table A on Municode, or in the city PDF of the schedule.
- 3Ask Development Services (480-782-3000) for the fee calculation for your site and the credit for any existing meter.
- 4Plan to pay at the building permit, or at the water connection if no building permit is required (38-11(A)(2)).
- 5For the meter's own installation charge, which is separate, see Chandler's meter installation fee page.
What do people get wrong?
- Myth: The fee is the meter cost. The installation charge in 50-9 is separate from the development fee in Chapter 38.
- Myth: Landscape meters pay sewer fees. Table A footnote 1 says no reclaimed water or wastewater fees for water-only connections.
- Myth: I will get a refund if I shrink the project. Section 38-15(E) says no refund when a development is later demolished or altered to reduce its size or number of units.
- Myth: The fees are the same in every city. Mesa's 2 inch meter carries a water fee of $41,166 and wastewater of $9,649, and Glendale's schedule differs by area.
Appendix A also lists per-square-foot street, fire, police and other fees. This page covers the utility fees only. It explains the code, and the adopted text on Municode governs.
How Do Other Valley Cities Handle It?
| Where | What applies | Source |
|---|---|---|
| Mesa | Mesa prices water and wastewater capacity fees by meter size in Table 1, so a 2 inch meter is $41,166 for water and $9,649 for wastewater. The fee is paid before the city installs a new or upsized meter, and an upsized meter pays only the increase. | Mesa City Code 8-10-13, Table 1 (Ord. 5970, 2025) Verified October 4, 2026 |
| Glendale | Glendale's schedule prices water and wastewater per meter in one part of the city ($37,973 total for a 2 inch meter) and shows $0 for every meter size in the other part. | Glendale Development Impact Fee Schedule (updated 2026-06-24) Verified October 4, 2026 |
This page explains the rule. The official text at the source above governs.
- Chandler City Code Chapter 38, system development fees (Municode)
- City of Chandler: System Development Fee Schedule, effective July 1, 2024 (PDF)
- City of Chandler Development Services: contacts and permits
- Mesa City Code 8-10-13, capacity fee (Municode)
- City of Glendale Development Impact Fee Schedule (updated 2026-06-24)
Water Supply and Pipes in Other Cities
- GlendaleWhat does a new commercial water meter cost in Glendale, and when is it set?
- ScottsdaleWhat does Scottsdale charge to install a water meter and service line?
- ScottsdaleWhen do Scottsdale commercial projects pay water and sewer development fees?
- SurpriseHow much does the City of Surprise charge to install a water meter?
- TempeTempe water tap and development fees by meter size for commercial service
- El MirageEl Mirage City Code 50.066: who installs water taps and service lines?
More Chandler Codes and Permits
- Water Supply and PipesWho fixes a broken water line in Chandler, the property owner or the city?
- Water Supply and PipesHow do you get a Chandler water meter tested for accuracy?
- Water Supply and PipesChandler water meter installation fee: 50-9 schedule by meter size
- Backflow PreventionChandler backflow testing: annual test, notices and water shutoff
- Permits and InspectionsCan you appeal a Chandler building official decision?
- Permits and InspectionsChandler City Code 29-1.3: violations, penalties and stop work orders
Related Rules and Questions
- MesaMesa water and sewer capacity fees for a commercial project: City Code 8-10-13 and 5-17-5
- ChandlerHow long does a commercial tenant improvement permit take in Chandler?
- FAQWhat sets the meter size and capacity fee for a commercial building?
- FAQWhat is a utility will-serve letter and when do you need one?
- FAQWho pays to extend a water or sewer main to a new commercial building?
- Commercial Plumbing