Three inches per hour. Phoenix amends IPC 1106.1 so vertical conductors, leaders, building storm drains, building storm sewers and their horizontal branches are all sized on 3 inches of rain per hour, in place of the base code's 100-year rate from its rainfall figures.
“shall be based on an hourly rainfall rate of three (3) inches per hour.”
- Applies to:
- Designers, plumbing contractors and owners sizing roof drains, leaders, conductors and building storm drainage on Phoenix commercial buildings
- Official fee:
- not applicable; storm drainage is reviewed with the plumbing plans and permit
- In force:
- 2024 IPC as amended by Phoenix (Ord. G-7397, eff. 2025-08-01), since August 1, 2025
- Last verified:
- October 4, 2026, against the official page
Every roof drain and storm pipe is sized for a design storm. Phoenix picks that storm for you: three inches of rain in an hour. The number sits in a one-sentence amendment, and it is the first input on any storm drainage calculation for a Phoenix building.
What does the Phoenix code say?
The model IPC 1106.1 sizes vertical conductors and leaders, building storm drains, building storm sewers and their horizontal branches from the 100-year hourly rainfall rate shown in its Figures 1106.1(1) through 1106.1(5), or from other rates based on approved local weather data. Phoenix replaces that. Its amended section reads that the size of those conductors, leaders, building storm drains, building storm sewers and horizontal branches "shall be based on an hourly rainfall rate of three (3) inches per hour."
The city struck the 100-year figure and the local weather data option. The justification says the 2024 UPC and the 2024 IPC list rainfall rates for Phoenix as 2.2 and 2.5 inches per hour, respectively, and that three inches per hour is recommended "to remain consistent with previous amendments and for ease of using the sizing tables." The cost note says the impact is minimal, "Due to drain and pipe size increase."
The city marks the amendment as approved in an earlier code cycle, and it is part of the 2024 code that Ordinance G-7397 put in force on August 1, 2025.
What do the key terms mean?
- Conductor or leader: the vertical pipe that carries roof water down from a roof drain.
- Building storm drain and storm sewer: the horizontal piping that carries storm water from the leaders to the point where it leaves the building.
- Hourly rainfall rate: the design rain in inches per hour that the drain and pipe sizes must be able to carry.
Who does this cover?
Designers, engineers and plumbing contractors sizing storm drainage on a Phoenix building, and the owners who pay for it. Roof drains on flat commercial roofs are the common case, since a large roof collects a lot of water into a few drains.
Quick check: how much does 3 inches per hour change?
The city's own justification says the IPC lists Phoenix at 2.5 inches per hour, so 3 inches per hour means 20 percent more design flow into the same roof. Roof flow scales with area and rain rate. Using the standard conversion of about 0.0104 gallons per minute per square foot for each inch per hour, a 10,000 square foot roof produces about 312 gallons per minute at 3 inches per hour, against about 260 at 2.5. That figure is our arithmetic, not city text, and a design uses the code's sizing tables.
| Rain rate used | Roof of 10,000 sq ft, approximate flow |
|---|---|
| 2.5 in/hr, the IPC figure the city cites for Phoenix | 260 gpm |
| 3 in/hr, the Phoenix amendment | 312 gpm |
| 2.2 in/hr, the UPC figure the city cites for Phoenix | 229 gpm |
What does this look like in real life?
- A new retail building draws its roof drainage on a sizing table. The designer starts from 3 inches per hour, not from the rainfall figures in the model code, and sizes each drain and leader from that.
- A tenant remodel adds a roof drain to an existing flat roof. The added drain and any new leader or storm branch use the 3 inch rate.
- The same firm designs a building in Chandler. The answer flips: Chandler has no local rate, so the model code's 100-year rate applies there, and the design cannot carry a Phoenix assumption across the city line.
- A design already uses 3 inches per hour for a Mesa project. Mesa writes the same 3 inches per hour into its amendment, so the assumption carries over.
What should you do next?
- 1Put 3 inches per hour at the top of the storm drainage calculation for any Phoenix building.
- 2Size roof drains, conductors, leaders, storm drains and storm sewer branches from it.
- 3Show the design rate on the plumbing plans so the reviewer sees it. Submit them through the city's current SHAPE PHX permitting process.
- 4Check how the code sizes secondary (overflow) drains for the same roof, and confirm with Planning and Development that the 3 inch rate carries over to them.
- 5For a project in another city, look up that city's rate before reusing the calculation.
What do people get wrong?
- "The model code figures apply." Phoenix replaced them with a fixed 3 inches per hour.
- "3 inches is the 100-year storm." The Phoenix text states a rate of three inches per hour with no return period. Tempe's amendment ties its 3 inches to the 100-year rate.
- "It only affects the roof drain." The section covers vertical conductors and leaders, building storm drains, building storm sewers and their horizontal branches.
How Do Other Valley Cities Handle It?
| Where | What applies | Source |
|---|---|---|
| Mesa | Mesa uses the same number. Its 2024 IPC amendment to 1106.1 says the sizing shall be based on an hourly rainfall rate of 3 inches per hour, adopted by Ordinance 5983. | Mesa City Code 4-5-2 (2024 IPC 1106.1) Verified September 29, 2026 |
| Tempe | Tempe also writes 3 inches per hour into its amendment, tied to the 100-year hourly rainfall rate: sizing shall be based on the 100-year hourly rainfall rate of three inches per hour. Its 1109.1 also points storm water work to the city's Storm Water Management Plan. | Tempe City Code 8-600 (2024 IPC 1106.1 and 1109.1) Verified September 29, 2026 |
| Chandler | Chandler has no local amendment to IPC 1106. Its 2024 IPC amendments touch only Chapter 1, 410.4 and 1003.3.7, so the model code's method applies: the 100-year hourly rate from the code's rainfall figures or approved local weather data. | Chandler City Code 29-4 Verified September 29, 2026 |
This page explains the rule. The official text at the source above governs.
Drains, Traps and Vents in Other Cities
More Phoenix Codes and Permits
- Drains, Traps and VentsPhoenix City Code 32A-24: On-Site Stormwater Retention for Commercial Sites
- Drains, Traps and VentsPhoenix City Code 32C-103: Who Maintains Retention Basins and Drywells
- Drains, Traps and VentsPhoenix City Code 32C-103: Can You Wash a Parking Lot Into the Storm Drain?
- Permits and InspectionsWhich building and plumbing codes does Phoenix enforce?
- Commercial PlumbingCan a Phoenix business get an annual permit for plumbing alterations?
- Backflow PreventionDo you need a permit to install or replace a backflow preventer in Phoenix?
Related Rules and Questions
- PhoenixCan you use PVC, CPVC or PEX water pipe outdoors in Phoenix?
- PhoenixWhat permit does a Phoenix business need for a plumbing remodel or tenant improvement?
- PhoenixWhich minor commercial plumbing jobs can be permitted online in Phoenix?
- PhoenixCan a Phoenix business dilute corrosive waste instead of neutralizing it?
- FAQWhat does code require for roof drains on a flat roof?
- FAQWhy do roof plumbing vents and roof drains need cleaning?
- FAQWhat plumbing code does Phoenix use?
- Commercial Plumbing