Maricopa County Zoning 1205: Retention Basins and the 36-Hour Rule

Verified September 29, 2026
In Short

In unincorporated Maricopa County, a commercial site must retain the 100-year, 2-hour storm falling on the whole site and empty it within 36 hours, under Zoning Ordinance Section 1205.7.6. Drywells must be ADEQ-registered, tested one by one, and cleaned by the owner at least every three years.

Official Source
Maricopa County Zoning Ordinance, Section 1205 Drainage Regulations (PDF)
Maricopa County Zoning Ordinance Section 1205.7.6 (Drainage Regulations)
“On-site runoff that has been retained shall be disposed of within 36 hours either by percolation, drywells or draining into an approved drainage way.”
Applies to:
Commercial, industrial, multi-family and institutional sites in unincorporated Maricopa County; owners, developers and engineers
In force:
Maricopa County Zoning Ordinance (June 2016 edition), Section 1205; Drainage Policies and Standards (revised August 22, 2018)
Last verified:
September 29, 2026, against the official page

Out in the unincorporated county, stormwater doesn't get to leave the lot. Section 1205 of the Maricopa County Zoning Ordinance makes a commercial site hold its own runoff from a big storm and get rid of it within 36 hours. The part owners forget comes years later: the county puts drywell cleaning on the owner, on a clock.

What does Section 1205.7.6 say?

The ordinance sets the size first: "The retention system shall be designed to receive and retain the volume generated from the 2-hour, 100-year runoff event falling over the entire development site including all rights-of-way, excluding off-site flows." That's the whole parcel plus the adjacent street right-of-way, not just the roof and parking lot.

Then the clock: "On-site runoff that has been retained shall be disposed of within 36 hours either by percolation, drywells or draining into an approved drainage way." The county's Drainage Policies and Standards explain why: "The purpose for the 36-hour drain time is vector control and to allow for the probability of a second severe storm following the previous storm." County Environmental Services says mosquitoes breed in standing water that lasts "at least 72 hours or 3 days," so a basin that drains on time never gets there.

The parts, in order:

  • Volume. The 100-year, 2-hour storm over the entire site. The county's plan review form adds "one (1) foot of freeboard."
  • Drywells don't count as storage. "Drywell volume shall not be used as part of the retention volume."
  • Drain-down. 36 hours, by soaking in, drywells or an approved drainage way.
  • Parking lots. No more than 25 percent of public parking can hold water, no deeper than 12 inches, and "Private parking areas shall not be used for runoff retention."
  • Drywells. Stormwater only, and "Proof of drywell registration with the Arizona State Department of Environmental Quality shall be required prior to final as-built approval or issuance of any drainage clearance."
  • Setbacks. Basins stay 25 feet from septic systems. Drywells sit at least 10 feet above saturated soil and 100 feet from any water supply well.
  • Paperwork. Commercial projects need a drainage report and plan sealed by an Arizona registered civil engineer, and a final drainage clearance before the final Certificate of Occupancy.

What do the key terms mean?

  • 100-year, 2-hour storm. A two-hour storm with a 1 percent chance of happening in any year. The engineer turns it into a volume with the manual's formula, V = C × (P/12) × A: runoff coefficient times rainfall depth times area.
  • Retention versus detention. Retention holds the water on site until it soaks in or drains away. It's not released to the street during the storm.
  • Drywell. A shaft that drains the basin into deeper soil. ADEQ now treats it as a Class V injection well.
  • Constant-head percolation test. The field test run on each finished drywell to set its real drain rate.
  • De-rating factor. The safety divisor applied to that test: 2 for sand and gravel, 3 for silts and loams, 5 for clay. The result can't be under 0.1 cubic feet per second per well.
  • Freeboard. Extra depth above the design water level, one foot here.

Who does this cover?

Commercial, industrial, multi-family and institutional projects in unincorporated Maricopa County, such as parts of New River, Rio Verde, Sun City West and county islands. The Planning and Development Department's Drainage Administrator enforces it.

This does not apply inside a city or town. The ordinance says it "shall not pertain to or otherwise regulate cities, towns or other incorporated municipalities." A site in Phoenix, Mesa or Surprise follows that city's drainage rules instead.

Quick check: will this pass county drainage review?

SituationOutcomeWhy
Basin sized for the 100-year, 2-hour storm, drains in 30 hoursMeets the ruleUnder the 36-hour limit
Basin that holds water for two days after a stormFails36-hour disposal limit in 1205.7.6
Drywell storage counted toward the retention volumeFailsDrywell volume can't be counted
Employee parking lot designed to pond 10 inchesFailsPrivate parking can't be used for retention
Customer lot ponding 12 inches on 20 percent of stallsMeets the ruleUnder 25 percent of public parking, 12 inch cap
As-built with no ADEQ drywell proofNo drainage clearanceProof of registration needed first
Drywell last cleaned four years agoOut of complianceMaintenance can't exceed three years

What does this look like in real life?

A contractor yard near New River. The engineer sizes a basin for the whole parcel plus half the road right-of-way, adds a foot of freeboard, and uses two drywells. Each drywell gets a constant-head test before the as-built, and the owner uploads proof of ADEQ registration.

A church in a county island. The design calls for ponding in the staff lot behind the building. Review kicks it back: private parking can't hold retention, so the basin moves to landscaping.

The same church gets annexed. Here the answer flips. Once the parcel is inside a city, Section 1205 no longer applies and the city's drainage manual controls any new work.

A basin that won't drain. Five years after opening, water sits for three days after each monsoon. The manual puts the fix on the owner: "Drywells that cease to drain a retention basin with 36-hours shall be replaced or refurbished by the owner or his representative."

What should you do next?

  1. 1Confirm the parcel is unincorporated on the county's parcel viewer or with Planning and Development before using these rules.
  2. 2Hire an Arizona registered civil engineer to prepare the sealed drainage report and plan.
  3. 3Test each drywell with a constant-head percolation test after it's built, and each basin with the ASTM D3385 double-ring test (two tests minimum per basin).
  4. 4Inventory the drywells with ADEQ in myDEQ and keep the proof for the as-built.
  5. 5Submit the certified as-built stating the system "will drain within 36 hours," then request the final drainage clearance before the Certificate of Occupancy.
  6. 6Put drywell cleaning on a schedule no longer than every three years, and keep the annual maintenance certification the landscaping and maintenance agreement calls for.

What do people get wrong?

  • "County rules apply everywhere in the county." Only unincorporated land. Cities write their own.
  • "The drywell adds storage." Its volume doesn't count toward retention.
  • "Any parking lot can double as a basin." Only public parking, only 25 percent of it, and only 12 inches deep.
  • "Maintenance is the city's or county's job." The standards say basins "are to be privately maintained," and drywell cleaning is the owner's responsibility.
  • "The 36-hour rule is just paperwork." It's the county's mosquito control line.

What happens if you skip it?

No as-built approval and no final drainage clearance means no final Certificate of Occupancy for a commercial building. After that, Chapter 15 of the zoning ordinance makes a violation a class 2 misdemeanor, or a civil penalty capped at the class 2 misdemeanor fine.

Retention and drywells are civil engineering work. When the water backing up is inside the building, from floor drains, restroom lines or the sewer, a licensed plumber is the right call.

How Do Other Valley Cities Handle It?

WhereWhat appliesSource
PhoenixRetain the 100-year, 2-hour storm and empty basins within 36 hours. Parking lot ponding is capped at six inches, and a basin with no public outfall needs 25 percent more volume.Phoenix City Code 32A-24; Stormwater Policies and Standards Manual 6.8
Verified September 29, 2026
MesaRetain up to the 100-year, 2-hour storm and drain it within 36 hours, 3 feet deep plus 6 inches of freeboard. Drywells are the least preferred method and need the City Engineer's written permission.Mesa Engineering and Design Standards 2025, Sec. 806
Verified September 29, 2026
ChandlerRetain the 100-year, 2-hour storm, sized to 110 percent and no deeper than 3 feet. City code makes it unlawful to let water stand in a retention basin longer than 36 hours.Chandler City Code 45-3 and 45-4
Verified September 29, 2026
GlendaleCommercial sites retain the full 100-year, 2-hour storm and dispose of it within 36 hours. Up to 75 percent of the volume may be stored on paved areas.Glendale City Code 18.5-10
Verified September 29, 2026

This page explains the rule. The official text at the source above governs.

Sources

Drains, Traps and Vents in Other Cities

Related Rules and Questions

Questions About Maricopa County Plumbing Code?

We work to code every day across the Valley. Call the dispatcher and we'll tell you what your project needs.