Phoenix Adopted Codes

Which building and plumbing codes does Phoenix enforce?

Verified September 28, 2026
In Short

Since August 1, 2025, Phoenix enforces the 2024 International Building, Residential, Mechanical, Fuel Gas and Plumbing codes and the 2024 Uniform Plumbing Code, all with Phoenix amendments. Plumbing plans may follow either the UPC or the IPC. Plans submitted after December 31, 2025 must follow the 2024 set.

Official Source
City of Phoenix Planning and Development: Phoenix Construction Code History
Phoenix Construction Code History (TRT 00550, Rev. 08/25), Ordinance G-7397
“Current Codes Adopted – Effective August 1, 2025 (Ordinance G-7397)”
Applies to:
Homeowners, contractors, plumbers, designers and property managers working in the City of Phoenix
Official fee:
not applicable
In force:
2024 Phoenix Building Construction Code (Ord. G-7397), since August 1, 2025
Last verified:
September 28, 2026, against the official page

Phoenix runs on the 2024 codes now. The City Council adopted them June 18, 2025, and they took effect August 1, 2025 under Ordinance G-7397. Phoenix bundles them with its own administrative rules and amendments and calls the package the Phoenix Building Construction Code (PBCC). The surprise for most contractors: plumbing designers can choose the Uniform Plumbing Code or the International Plumbing Code, and either one comes with Phoenix changes.

What does the Phoenix code history say is in force?

The city's code history opens its list with "Current Codes Adopted – Effective August 1, 2025 (Ordinance G-7397)." Those are the codes Phoenix inspectors enforce today. The pieces that touch plumbing and gas:

  • 2024 International Plumbing Code (IPC), with Appendices C and E.
  • 2024 Uniform Plumbing Code (UPC), with Appendices A, B, C, I and M.
  • 2024 International Fuel Gas Code (IFGC) for gas piping and appliances.
  • 2024 International Building Code (IBC), whose Chapter 1 holds the Phoenix administrative provisions on permits, inspections and fees.
  • 2024 International Residential Code (IRC) and 2024 International Mechanical Code (IMC), which overlap on houses and water heater venting.
  • 2024 International Swimming Pool and Spa Code, for pool and spa plumbing.

The city list also shows the prior set: the 2018 codes under Ordinance G-6463, effective July 6, 2018.

What do the key terms mean?

  • PBCC: the Phoenix Building Construction Code, meaning the model codes plus Phoenix's administrative provisions and amendments.
  • Amendment: a Phoenix change to a model code. The model book is the starting point. The amended text is the rule.
  • Administrative provisions: the permit, inspection, fee and licensing rules in IBC Chapter 1 as Phoenix rewrote it.
  • Initial review: the first time plans are submitted. The city ties the code edition to that date, not to the date you pull the permit.

Phoenix's own text on the plumbing choice reads that "the provisions of the Uniform Plumbing Code or International Plumbing Code, as amended, shall apply" to installing, altering, repairing and replacing plumbing (Section 101.4.3). Read that as a choice the design makes once. It is a reading, not a defined rule, that mixing sections of both codes in one design would not fit the wording.

Who does this cover?

Anyone doing permitted work inside the City of Phoenix: homeowners, contractors, tenants' contractors and designers. It does not cover work in Mesa, Chandler, Glendale or other cities, which adopt their own editions. Arizona statutes such as the contractor licensing law sit outside the building code and apply everywhere.

Which code set applies to my plans? A quick check

The implementation notice sorts projects by the date plans were first submitted.

Your situationCode that appliesWhy
Plans first submitted on or after August 1, 20252024 PBCCThe notice says initial reviews from that date must comply
Plans submitted before August 1, 20252018 PBCC for later resubmittalsThe notice allows permits to be bought within one year of plan approval
Complete plans submitted August 1 to December 31, 2025, in a listed case2018 PBCC allowedProjects already in development review need PDD Team Leader or Deputy Director approval, or the Building Official allows it case by case
Plans submitted after December 31, 20252024 PBCC, no exceptionsThe notice says all such plans must comply
A standard plan approved under the 2018 code2018 code until July 31, 2026That date has passed, so new use needs the 2024 code

What does this look like in real life?

  • Restaurant tenant improvement filed in October 2025. The owner wants to stay on the 2018 code because the drawings are done. Plans first submitted after August 1, 2025 fall under the 2024 set unless one of the notice's exceptions fits: a project already in development review, an earlier submittal, or a case-by-case approval.
  • Tenant improvement filed in February 2026. No exception exists. The plans follow the 2024 PBCC, including Phoenix's grease interceptor amendments.
  • Design drawn to the UPC. It stays on the UPC. Section 101.4.3 lets the plans follow either code, so nobody has to redraw it to the IPC.
  • A contractor working Phoenix and Gilbert on the same day. The Phoenix job follows the 2024 codes with Phoenix amendments. Gilbert's town code adopts the 2018 IPC, so the same fixture can face different rules across a city line.

What should you do next?

  1. 1Open the Planning and Development Department's building code page and download the amendment PDFs for the code your plans use (2024 IPC or 2024 UPC) and the 2024 IBC Chapter 1 administrative provisions.
  2. 2Pick one plumbing code for the design and note it on the plans.
  3. 3Compare your first submittal date with the table above.
  4. 4Read the amended sections for your job before drawings are final. Grease interceptors, backflow, secondary backflow protection and low-slope sewers all carry Phoenix changes.
  5. 5Submit through the SHAPE PHX portal, where commercial plan review and inspection permits went live April 27, 2026. PDD's main line is 602-262-7811.

What do people get wrong?

  • "Phoenix only uses the UPC." The code says UPC or IPC, and Phoenix amends both.
  • "The 2024 codes started in 2024." Council adopted them June 18, 2025, effective August 1, 2025.
  • "The 2018 code still works for new plans." Not for plans submitted after December 31, 2025.
  • "The model code text is the whole rule." Phoenix amends the model books. Read amendment PDFs in the PDF itself, because struck-through text is easy to miss in a copy and paste.

How Do Other Valley Cities Handle It?

WhereWhat appliesSource
ChandlerChandler adopts the 2024 International Plumbing Code by reference, with Chandler amendments, and does not name the Uniform Plumbing Code.Chandler City Code Chapter 29, Article IV (Plumbing Code)
Verified September 28, 2026
MesaMesa reviews plumbing plans to the 2024 IPC with Mesa amendments, and deletes IPC Sections 101.4 through 116.5 in favor of Mesa's own administrative code.Mesa City Code 4-5-2 (amendments to the 2024 International Plumbing Code)
Verified September 28, 2026
GilbertGilbert adopts the International Plumbing Code, 2018 Edition, with its Appendix B, an older edition than Phoenix and Chandler.Gilbert Town Code 10-34
Verified September 28, 2026

This page explains the rule. The official text at the source above governs.

Sources

Permits and Inspections in Other Cities

More Phoenix Codes and Permits

Related Rules and Questions

Questions About Phoenix Plumbing Code?

We work to code every day across the Valley. Call the dispatcher and we'll tell you what your project needs.