Most Phoenix permits expire 24 months after they are issued under PBCC Section 105.5. The building official can extend one in writing for up to a year at a time if you ask before it expires, and an expired permit can be reinstated within a year. Permits for work started without a permit get only 12 months.
“shall expire 24 months after the date of permit issuance, unless an extension is granted in accordance with section 105.5.1.”
- Applies to:
- Homeowners, owner-builders, contractors and commercial permit holders with an open Phoenix building, plumbing, gas or mechanical permit
- Official fee:
- One-time permit extension 50% of the current permit fee, paid before expiration; reinstatement within one year of expiration 50% of the current permit fee (PDD Fee Schedule, Appendix A.2, Ord. G-7465, effective 2026-01-20)
- In force:
- 2024 IBC Chapter 1 with Phoenix amendments, Ordinance G-7397, since August 1, 2025
- Last verified:
- October 4, 2026, against the official page
In several Valley cities a permit dies at 180 days if nobody calls for an inspection. Phoenix works differently: its 2024 administrative code puts most permits on a fixed 24-month clock from the day they are issued. That gives a long runway, but it runs whether or not work is moving, and the rules for extensions and reinstatement are strict about timing.
What does PBCC Section 105.5 say?
Phoenix replaced the model code's 180-day language. The amended section reads: "Every permit issued, except demolition permits and permits subject to section 114 of this code, shall expire 24 months after the date of permit issuance, unless an extension is granted in accordance with section 105.5.1."
Section 105.5.1 covers extensions: "The building official is authorized to grant, in writing, one or more extensions of time, for periods not more than one year each. The extension shall be requested in writing prior to permit expiration and justifiable cause demonstrated." The application comes with a non-refundable fee from Appendix A.2 of the City Code, and the building official may adjust it based on the inspection hours left, plus an administrative fee at the general hourly plan review rate with a two-hour minimum.
Section 105.5.2 covers reinstatement of an expired permit, for up to one year, if two conditions are both met: "No changes have been made or will be made in the original plans and specifications for such work," and "The original permit expired less than one year from the request to reinstate." It has to be requested in writing with justifiable cause and a non-refundable fee.
Permits issued under Section 114, for work started without a permit, follow their own clock: "All work must be completed within 12 months from date of permit issuance." Those get "A one-time extension, not-to-exceed 90 calendar days," and a reinstated Section 114 permit cannot run past 90 calendar days from reinstatement.
In short:
- Regular permits: 24 months from issuance.
- Extension: in writing, before expiration, with justifiable cause, up to one year each.
- Reinstatement: in writing, within a year of expiration, and only with no plan changes.
- Work-without-permit (Section 114) permits: 12 months, one 90-day extension.
- Demolition permits have their own 60-day completion rule.
What do the key terms mean?
- Issuance: the date the permit is issued, not the date you applied or started work.
- Justifiable cause: the code does not define it. The request has to explain why the work could not finish in time.
- Reinstatement: reviving a permit that already expired, as opposed to extending one that is still active.
- Section 114 permit: a permit issued after the city finds work was started without one.
Who does this cover?
Anyone holding a Phoenix building, plumbing, gas, mechanical or electrical permit under the building construction code: homeowners, owner-builders and contractors on residential and commercial jobs.
This does not apply to demolition permits, which expire under Section 105.5.3 if the work isn't completed within 60 days, or to the permit application itself, which has separate abandonment rules in Section 105.3.2.
Quick check: where does my permit stand?
| Situation | Outcome | Why |
|---|---|---|
| Permit issued 20 months ago, work nearly done | Still active; finish or request an extension before month 24 | 105.5 and 105.5.1 |
| Permit expires next week, final not passed | Request an extension in writing now and pay the fee | Extensions must come before expiration |
| Permit expired 4 months ago, same plans | Can ask for reinstatement | Under one year, no plan changes |
| Permit expired 4 months ago, design changed | Reinstatement conditions not met | 105.5.2 requires no changes to plans |
| Permit issued after a work-without-permit notice | 12 months to finish | Section 114.1.4.1.5 |
| Demolition permit | Work completed within 60 days | Section 105.5.3 |
What does this look like in real life?
- A homeowner's repipe stalls. The plumbing permit was issued in March of one year. With a 24-month term it is still good the following March, even if nothing happened for six months. In Avondale or Cave Creek the same pause could have expired it.
- A tenant improvement runs long. The contractor sees month 23 coming and files a written extension request with the fee before the permit lapses. The building official can grant up to a year.
- A garage conversion caught without a permit. The owner gets a Section 114 permit. The answer flips: this permit has 12 months, not 24, and only one 90-day extension.
What should you do next?
- 1Look up the permit's issue date and add 24 months, or 12 months for a Section 114 permit.
- 2Schedule inspections with time to spare before the expiration date.
- 3If you need more time, submit a written extension request with your justifiable cause before the expiration date. The PDD Fee Schedule (January 20, 2026) lists a one-time permit extension at 50% of the current permit fee, with application and payment due before the expiration date.
- 4If the permit already expired and plans are unchanged, request reinstatement in writing within a year; the fee schedule lists it at 50% of the current permit fee.
- 5If the plans changed, ask Planning and Development which new submittal applies.
What do people get wrong?
- "No inspection in 180 days kills the permit." That's the model code language Phoenix replaced with a 24-month term from issuance.
- "You can extend after it expires." The code says the extension must be requested "prior to permit expiration."
- "Any expired permit can be revived." Reinstatement requires no plan changes and a request within a year of expiration.
- "Permits after a violation get the same time." Section 114 permits have 12 months and one 90-day extension.
How Do Other Valley Cities Handle It?
| Where | What applies | Source |
|---|---|---|
| Avondale | Avondale runs a shorter clock: a permit expires if an inspection has not been requested and approved within 180 days of issuance, or if work goes inactive for 180 days. | Avondale Building Services, Inspections Verified October 4, 2026 |
| Cave Creek | Cave Creek's amended code makes a permit invalid unless work starts within 180 days of issue, shown by a passed inspection, or if work stops for 180 days, and the building official may grant one written extension of up to 180 days. | Cave Creek Ordinance 2025-08, IBC 105.5 as amended Verified October 4, 2026 |
| Chandler | Chandler lets the building official reinstate an expired permit for a reinstatement fee if it has not been expired more than one year and code requirements that would affect the project have not changed. | Chandler City Code 29-6.9 (IRC R105.5.1 as amended) Verified October 4, 2026 |
This page explains the rule. The official text at the source above governs.
Permits and Inspections in Other Cities
- ChandlerCan you appeal a Chandler building official decision?
- ChandlerChandler City Code 29-1.3: violations, penalties and stop work orders
- ChandlerWhat does Chandler City Code 29-4 change in the International Plumbing Code?
- ChandlerWhat must be finished before a Chandler business gets its certificate of occupancy?
- Fountain HillsWhich plumbing code does Fountain Hills use? 2024 IPC and IRC, since September 1, 2025
- GilbertGilbert Town Code 66-8: the permit to dig a street or alley for a water or sewer connection
More Phoenix Codes and Permits
- Permits and InspectionsWhich building and plumbing codes does Phoenix enforce?
- Permits and InspectionsPBCC 110.3.10.1: Which plumbing inspections does Phoenix require?
- Permits and InspectionsHow does Phoenix calculate a plumbing permit fee?
- Permits and InspectionsPBCC Section 119: Who may do permitted plumbing work in Phoenix?
- Permits and InspectionsWhat happens if plumbing work is done without a permit in Phoenix?
- Commercial PlumbingCan a Phoenix business get an annual permit for plumbing alterations?
Related Rules and Questions
- PhoenixWhat permit does a Phoenix business need for a plumbing remodel or tenant improvement?
- FAQHow long does a Scottsdale plumbing permit last?
- FAQHow can I find a Phoenix property’s plumbing permit and inspection records?
- FAQHow much does a plumbing permit cost in Phoenix and how long does it take?
- Commercial Plumbing