Commercial gas lines

Restaurant Gas Line Installation in Phoenix

Btu load, pipe sizing, permit drawings, the pressure test and the Southwest Gas meter set, scheduled backward from your opening date.

Short answer

A new restaurant gas line is sized from the total Btu load of every appliance, drawn up for the city, installed with a shutoff at each appliance, pressure tested and inspected. Southwest Gas sets or upgrades the meter only after the city clearance reaches it. Start early, because the utility's lead times can run 6 to 12 weeks.

The rules that apply

Each rule links to the official text we read it from. Cities change these, so check the source before a big decision. Last checked 2026-10-04.

Pipe is sized for everything firing at once

Phoenix (2024 IFGC)

Gas demand is the sum of the maximum input of the appliances served, assuming all could run at full capacity at the same time. A lower diversity figure is allowed only where diversity can be established.

Source: IFGC 402.2 (Phoenix Fuel Gas Code 2024)

What the permit drawings must show

Phoenix

The plans mark the gas meter as existing or new with its capacity, list every appliance and its Btu input, and give the total developed length from the meter to the most remote appliance. Gas at 2 psi or more needs a Southwest Gas confirmation letter in the drawing set.

Source: Phoenix Plan Review Checklist, Gas Piping (TRT/DOC/00708)

Elevated pressure needs utility approval first

Southwest Gas, Central Arizona

Standard delivery is 1/4 psi (7 inches water column). A 2 or 5 psi request needs written approval from Southwest Gas Engineering before the house line is installed, and is not granted if the interior pipe would be smaller than 4 inches at standard pressure.

Source: Southwest Gas New Commercial Business package

No meter until the city clears the line

Southwest Gas, Central Arizona

Southwest Gas must receive the city's gas inspection and clearance. The meter is set no sooner than 5 working days after that for loads under 1,000 cubic feet per hour, and 8 working days above it.

Source: Southwest Gas New Commercial Business package, meter set process

Test pressure is higher in Mesa

Mesa

Mesa replaces the base test with at least 10 psi gauge, and at least 60 psi for welded piping or gas above 14 inches water column. Dial gauges must read in 0.1 psi steps for tests of 10 psi or less.

Source: Mesa City Code 4-7-2, IFGC 406.4.1 and 406.4.3

The hood system shuts off the gas

Phoenix (2024 IFC)

When the hood's fire-extinguishing system activates, it must automatically shut down fuel and electric power to the cooking equipment, and the reset must be manual.

Source: Phoenix Fire Code 904.14.2

Start with the opening date and work backward

The gas line is usually the item that decides whether a restaurant opens on time, because two clocks run at once: the city's and Southwest Gas's. Southwest Gas's commercial package for Central Arizona says underground work (main, service line and riser) typically starts at least 6 weeks after the paperwork is signed, and a main design, permit, land rights or elevated pressure adds another 6 weeks. A load over 1,000 cubic feet per hour may need a rotary meter designed and built, which takes 2 weeks, or 4 over 7,000.

So the first job is the load list, not the pipe. Once we know every appliance and its rating, you can apply to Southwest Gas while the drawings go through the city. Doing those in order instead of in parallel is how kitchens end up finished and waiting on a meter.

What we need from you on the first call

Most of the design comes from four things you probably already have:

  • The equipment schedule. Make and model of every range, fryer, griddle, broiler, oven, wok, steamer and water heater, so we can read the Btu input off the spec sheets.
  • The floor plan. Where the cooking line, the water heater and the meter sit. Distance drives pipe size as much as load does.
  • The space history. A second-generation space has an existing meter and piping we check before we plan around them.
  • Your opening target. We schedule the pressure test and inspection backward from it.

If you plan a second fryer next year or patio heaters for the winter, tell us now. Section 402.2 of the fuel gas code sizes pipe on everything running at once, and adding capacity during the build costs far less than re-piping a kitchen that's open for service.

Drawings, permit and the 2 psi decision

Phoenix's gas piping plan review checklist asks for the meter marked existing or new with its capacity, each appliance with its Btu input, sizing calculations with the code table used, and the total developed length from the meter to the farthest appliance. We prepare that set and submit it.

The pressure question gets settled here too. Southwest Gas delivers at a quarter pound (7 inches water column) as standard. A building can ask for 2 or 5 psi, which lets smaller pipe carry the same gas, but the utility's elevated pressure form says it won't be granted if interior pipe would be smaller than 4 inches at standard pressure. Most single restaurants stay at standard pressure. Our 2 psi gas system guide covers when it makes sense.

The install, valve by valve

The piping usually runs along the wall behind the line to a manifold, with a branch dropping to each appliance. Every branch gets a shutoff valve within 6 feet of the appliance and ahead of the connector, a sediment trap where the appliance needs one, and a listed connector with a restraint cable for anything on casters. Our page on kitchen equipment gas hookups goes through the appliance end in detail.

The hood's fire-extinguishing system ties into the gas piping. Phoenix's fire code requires it to shut off fuel to the cooking equipment automatically when it discharges, with a manual reset. We install the gas shutoff valve in the line; HQ does not install or service the suppression system itself, so your fire suppression contractor and your hood installer are part of the same schedule. See how the hood gas shutoff valve works.

Test, inspection and turn-on, city by city

Before any gas goes in, the new piping is pressure tested with air or nitrogen and inspected while the joints are still exposed. Phoenix lists it as commercial inspection 235, gas piping. The test itself differs across the Valley:

CityMinimum test for new commercial gas piping
Phoenix1.5 times working pressure, never under 3 psig; half an hour per 500 cubic feet of pipe volume
Mesa10 psi; 60 psi for welded pipe or gas above 14 inches water column
Gilbert10 psi held at least 15 minutes; 60 psi for at least 30 minutes on welded or elevated-pressure pipe

Phoenix amends only Chapter 1 and the flange section of the 2024 fuel gas code, so the base test applies there. Our commercial gas pressure testing page has the full city list.

Once the inspector signs off, the city sends the clearance to Southwest Gas. The meter goes in no sooner than 5 working days later (8 for loads over 1,000 cubic feet per hour). Southwest Gas runs its own leak check at turn-on, and the code requires each appliance connection checked and the line purged before the kitchen fires up.

When a new install is the wrong answer

Not every kitchen change is a new gas line. Phoenix's gas clearance table, published with Southwest Gas and the Arizona Corporation Commission, says replacing an appliance in kind with no piping change needs no permit. If you're just swapping a worn fryer for the same size, that's a hookup, not an install. If you're adding equipment to a working kitchen, start with whether the existing line can carry it.

A few things sit outside our work: the meter and service line belong to Southwest Gas, the hood suppression system belongs to a fire suppression contractor, and portable propane equipment is not something we service.

How HQ handles a restaurant gas job

We take the job from load list to meter set: Btu calculations, drawings and the permit, black iron piping, valves, sediment traps, connectors and restraints, the pressure test, the inspection and the clearance hand-off to Southwest Gas. We're licensed and insured, and you get a free estimate with an upfront price before work starts. Related: commercial gas line service, restaurant plumbing and gas leak inspection for an existing kitchen that needs documented results.

FAQ

Restaurant Gas Line Installation: common questions

Anything else, call (602) 675-1555.

What's involved in a restaurant kitchen gas line install?

A restaurant gas install starts with a load count: every appliance's Btu rating, added up, sets the pipe size and tells Southwest Gas what meter you need. Then come permit drawings, black iron piping with a shutoff at each appliance, listed hoses and restraints for equipment on casters, a pressure test, a city inspection and the gas turn-on.

Read full answer: What's involved in a restaurant kitchen gas line install?
How do I get a bigger Southwest Gas meter for my business?

Ask Southwest Gas early, with a load list: every gas appliance and its Btu input, the delivery pressure you need, and your plans. The utility owns the meter, picks its size and may charge for the change. Your plumber resizes and permits the pipe on your side, and the city clearance goes to Southwest Gas.

Read full answer: How do I get a bigger Southwest Gas meter for my business?
What is a 2 psi gas system, and why do businesses use it?

A 2 psi system gets gas from Southwest Gas at about 2 pounds per square inch instead of the standard quarter pound, and regulators drop it back down near each appliance. Smaller pipe then carries the same gas. Southwest Gas approves it in writing only for systems that would need 4 inch or larger pipe, or equipment that needs it.

Read full answer: What is a 2 psi gas system, and why do businesses use it?
Why did the kitchen hood gas valve shut off my gas?

The hood gas valve is an automatic shutoff the fire code requires on the gas feeding cooking equipment under a hood. It closes when the fire suppression system goes off and, on electric valves, when building power drops or the hood panel shows certain faults. It stays shut until someone resets it by hand.

Read full answer: Why did the kitchen hood gas valve shut off my gas?