Under El Mirage City Code 50.066(B), the developer or property owner, subject to city approval, installs new water connections: the tap on the main, the service line, valves and the meter box or vault. The owner also pays the city's associated fees before the city installs the meter. Commercial use needs its own meter and connection.
“The developer/property, subject to city approval, shall be responsible for installing new water connections, including tapping water mains, installing water service lines, valves and meter boxes or meter vaults.”
- Applies to:
- Owners, developers, general contractors and plumbing contractors bringing a new water connection to an El Mirage property
- Official fee:
- Installation fees are set by council resolution. The linked FY26-27 document is marked proposed; obtain the adopted schedule and project charges from the city
- In force:
- El Mirage City Code Ch. 50, Water (Ord. O10-06-08 and later amendments)
- Last verified:
- October 4, 2026, against the official page
El Mirage puts new water-connection installation on the developer or property owner, subject to city approval. If you are building or adding a commercial space, the code says who digs, who pays, and what has to happen before a meter goes in.
What does El Mirage City Code 50.066 say?
Subsection (B) is the rule: "The developer/property, subject to city approval, shall be responsible for installing new water connections, including tapping water mains, installing water service lines, valves and meter boxes or meter vaults." The same subsection adds that "It is the developer's/property owner's responsibility to pay all other associated city fees prior to the city installing a water meter."
Two other rules in Chapter 50 fit around it. All water the city sells is metered by meters "owned and maintained by the city," so the city sets the meter even though the owner builds everything up to it. And any water service for commercial use may not be included in a residential service account: it must have a separate meter and connection.
Fees for water meter installations are "established by resolution of the Council," so the amounts are not in the code itself.
What do the key terms mean?
- Water connection: the tap on the main, the service line to the property, the valves and the meter box or vault, as the code lists them.
- Meter box or meter vault: the enclosure that holds the city-owned meter. The owner's side builds it, and the city installs the meter in it.
- Subject to city approval: the city reviews the connection before it is built. Work in a public street also needs a city right-of-way permit through Engineering.
- Resolution of the Council: the vote that sets the fee amounts, which is why the numbers can change each budget year.
Who does this cover?
Developers and property owners connecting a new building, a new commercial suite or a larger service to the El Mirage water system, and the licensed contractors they hire. It does not cover fixing a leak on an existing service line, which is a repair permit question, and it does not cover fire lines, which run under separate fire-service rules.
Quick check: who does what on a new water connection?
| Step | Who | Source |
|---|---|---|
| Tap the water main | Developer or owner, with city approval | 50.066(B) |
| Install the service line and valves | Developer or owner | 50.066(B) |
| Install the meter box or vault | Developer or owner | 50.066(B) |
| Pay associated city fees | Developer or owner, before the meter is set | 50.066(B) |
| Own, set and maintain the meter | City | Ch. 50 |
| Commercial use | Separate meter and connection | Ch. 50 |
| Meter fee amounts | Council resolution and the city fee schedule | Ch. 50 |
What does this look like in real life?
A new retail building on a vacant lot. The owner's contractor taps the main, runs the service line and sets the vault after the city approves the plans. The owner pays the city's fees, then the city sets the meter. The linked FY26-27 document is marked "Proposed Comprehensive Fee Schedule" even though it lists a July 1, 2026 effective date. Obtain the adopted meter charge from the city rather than budgeting from that document alone.
A shop added to a house on the same lot. The commercial space cannot share the home's residential account. It needs its own meter and connection, which means a second tap or a separate line and a second meter fee.
The edge case: a tap that reaches under the street. Approval under 50.066 covers the connection. A trench in the public street also needs a right-of-way permit from Engineering and a licensed contractor, and the street has to be restored afterward.
What should you do next?
- 1Confirm the property is served by an El Mirage main and find where it runs. Call Arizona 811 before any digging.
- 2Decide the meter size with your engineer or plumbing designer, because the fee follows the size.
- 3Ask the city's Permit Center how to submit connection plans and which Engineering approvals and right-of-way permits apply to the job.
- 4Hire a licensed contractor to make the tap, run the service line and set the valves and vault.
- 5Pay the associated city fees before asking the city to set the meter.
- 6Schedule the inspections the permit requires, then ask the city to install the meter.
What do people get wrong?
- "The city taps the main for me." In El Mirage the code puts the tap on the developer or owner, with city approval.
- "A commercial suite can share the house account." Commercial water service needs its own meter and connection.
- "The meter fee is in the code." The amounts are set by council resolution and change with the fee schedule. Check the current schedule.
- "Once the vault is built the water is on." The city installs the meter, and only after the fees are paid.
Full text and source
The rule is El Mirage City Code 50.066(B) on American Legal, with the meter and commercial service rules elsewhere in Chapter 50. The city's answer for your project, not this summary, decides a real dispute.
How Do Other Valley Cities Handle It?
| Where | What applies | Source |
|---|---|---|
| Mesa | The applicant extends the water main where needed, and the city sets meters and makes the connections. The owner does not tap the main. | Mesa City Code 8-10-4 Verified September 29, 2026 |
| Surprise | Laying water or sewer lines in public streets, right-of-way, alleys or city property requires a city construction permit first. | Surprise Municipal Code 58-425 and 58-218 Verified September 29, 2026 |
This page explains the rule. The official text at the source above governs.
- El Mirage City Code Sec. 50.066, Deposits; service connection charges (American Legal)
- El Mirage FY26-27 comprehensive fee document, marked proposed (City of El Mirage)
- El Mirage Permit Center (City of El Mirage)
- Mesa City Code 8-10-4, Minimum requirements for potable water service (Municode)
- Surprise Municipal Code Sec. 58-425, Permit required (Municode)
Water Supply and Pipes in Other Cities
- MesaWho pays for a new commercial water service in Mesa? Main extension, meters and easements under City Code 8-10-3 and 8-10-4
- ChandlerChandler water meter installation fee: 50-9 schedule by meter size
- PhoenixCan you use PVC, CPVC or PEX water pipe outdoors in Phoenix?
- PhoenixWho is responsible for the water line to your Phoenix property, the city or you?
- TempeTempe water tap and development fees by meter size for commercial service
- Valley-WideWater and Sewer Main Extensions: Who Pays and Who Builds, by City