Glendale City Code 33-126 to 33-129: sewer tap permit and who digs

Verified October 4, 2026
In Short

In Glendale, no one may uncover or connect to a public sewer without a written city permit, and a building connection also needs a valid city plumbing permit first. The owner pays for the building connection and exposes the main, but the city itself makes the tap. Right-of-way work needs additional permits and a specially licensed contractor.

Official Source
Glendale City Code Sec. 33-126: Permit (Municode)
Glendale City Code Secs. 33-126, 33-127 and 33-129
“No unauthorized person shall uncover, make any connections with, take any action to alter, adversely impact or otherwise affect any public sewer or appurtenance thereof without first obtaining a written permit from the City.”
Applies to:
Owners, developers and contractors connecting a building to a Glendale public sewer or working on a tap in the street
Official fee:
tap charge set by the city; the city's June 2026 ADU estimate lists a right-of-way permit of $443.60 and a right-of-way review fee of $35.88
In force:
Glendale City Code Ch. 33, Art. III, Div. 2 (Ord. 3003, 2016)
Last verified:
October 4, 2026, against the official page

Connecting a new building to the Glendale sewer looks like one job, but the code splits it between three parties: the owner, the city crew and the contractor. Getting the order wrong can stall a project at the street, so it helps to know who does what before anyone opens the ground.

What do Glendale City Code 33-126 to 33-129 say?

Section 33-126(a) is the permit rule: "No unauthorized person shall uncover, make any connections with, take any action to alter, adversely impact or otherwise affect any public sewer or appurtenance thereof without first obtaining a written permit from the City."

Subsection (b) adds that anyone applying for a building connection "shall present a valid plumbing permit issued by the City as a prerequisite for the approval of the requested building connection." Subsection (c) covers any other action that may affect the city sewer: the applicant describes the action and its expected impact, with the city approval fee.

Section 33-127 puts the cost on the owner: building connections are "installed at the property owner's expense" to city building codes, and the city approves the design, number, location, manner of connection and size. Connections go on lateral sewers only, unless the city specifically authorizes otherwise. The city may perform the connection itself for lines of four inches or more, and the owner then pays a connection fee.

Section 33-129 covers the tap itself: "The City shall make all taps from the City's sewer system." The owner makes the cuts to expose the main, provides shoring when required, and furnishes and installs the saddle tee with collar or wyes. A tap charge set by the city is paid before the tap is made.

What do the key terms mean?

  • Building connection: the connection from a building's sewer to the public sewer.
  • Appurtenance: a structure that belongs to the public sewer, such as a manhole.
  • Lateral sewer: the smaller sewer line that serves a street or block; building connections go on these unless the city says otherwise.
  • Wet tap: a tap made into a sewer that is in service. The section requires the city to make it.

Who does this cover?

Owners, developers and contractors connecting a building to a Glendale public sewer, and anyone opening the ground near a public sewer. It does not cover private lines on the owner's lot, which follow the plumbing permit rules, or the repair of an existing line, which is covered by Sec. 33-217.

Quick check: who does what?

StepWhoSection
Valid plumbing permitOwner or contractor, before the connection is approved33-126(b)
Written permit to touch the public sewerApplicant, from the city33-126(a)
Design, location and size approvedCity33-127(a)
Expose the main and provide shoringOwner33-129
Furnish and install the saddle tee or wyesOwner33-129
Make the tapCity crew33-129
Tap chargeOwner, paid before the tap33-129
Cost of the building connectionOwner33-127(a)

What does this look like in real life?

A new restaurant pad with a sewer in the street. The owner's contractor has the plumbing permit, gets the written city permit, digs to expose the main and supplies the saddle tee. The city crew makes the tap after the charge is paid.

A home addition with a new accessory dwelling unit. The city's ADU sheet says a separate water meter needs a new water tap to the city main in the street or right-of-way, and that work in the right-of-way requires additional permits and a specially licensed contractor. Its June 2026 estimate lists a right-of-way permit at $443.60 and a right-of-way review fee at $35.88. Those numbers come from the ADU estimate, not from a general fee schedule, so confirm the current amounts for your project.

The edge case: the city performs the connection. For lines of four inches or more, the city may make the whole connection if it thinks that is in its best interest. The owner then pays a connection fee instead of doing the work.

What should you do next?

  1. 1Confirm the plumbing permit is issued. Without it the city will not approve the building connection.
  2. 2Ask the Development Services Center (5850 W Glendale Ave, 623-930-2800) which written permit and approval fee apply to your connection.
  3. 3Get the connection design, location and size approved by the city.
  4. 4Hire a contractor able to work in the right-of-way. Ask the city which license and additional permits your job needs.
  5. 5Call Arizona 811 before any excavation.
  6. 6Pay the tap charge before the tap date, expose the main with shoring when required, and set the saddle tee.
  7. 7Schedule the city crew for the tap and keep the permits and receipts with the project file.

What do people get wrong?

  • "My plumber taps the main." In Glendale the city crew makes the tap. The owner prepares the excavation and the fitting.
  • "The plumbing permit covers the street." The plumbing permit is a prerequisite, and the sewer permit is separate.
  • "The ADU fees are the general fees." The $443.60 and $35.88 figures come from an ADU estimate sheet.
  • "Every city works this way." Surprise sends its street-dig permit to the city and Mesa sends it to the City Engineer.

Full text and source

The rules are Glendale City Code Secs. 33-126, 33-127 and 33-129 on Municode. They are short, so read them yourself. The city's answer for your project, not this summary, decides a real dispute.

How Do Other Valley Cities Handle It?

WhereWhat appliesSource
SurpriseDigging to lay sewer pipe in public streets, right-of-way, alleys or city property needs a city construction permit first, and doing it without one is a class 1 misdemeanor.Surprise Municipal Code 58-425
Verified September 29, 2026
MesaIt is unlawful to dig up a street or alley to connect to the sewer without first getting a permit from the City Engineer, or to leave it unrestored afterward.Mesa City Code 8-4-4
Verified September 28, 2026
ScottsdaleNo excavation in a street, alley or right-of-way to connect to the sewer without complying with the city's right-of-way permit article, and the street must be restored to its original condition.Scottsdale Revised Code 49-115
Verified September 28, 2026

This page explains the rule. The official text at the source above governs.

Sources

Sewer Lines in Other Cities

More Glendale Codes and Permits

Related Rules and Questions

Questions About Glendale Plumbing Code?

We work to code every day across the Valley. Call the dispatcher and we'll tell you what your project needs.