What pressure test does Chandler require on new gas piping?

Verified September 29, 2026
In Short

Chandler's Homeowner Building Permit Manual requires new gas piping to be tested at no less than 1.5 times the proposed maximum working pressure and never below 3 psig, for at least 10 minutes. Most homes, propane included, test at 3 psig. The test runs through the open valve and flex line, capped at the appliance.

Official Source
Chandler Homeowner Building Permit Manual, Gas Permits (City of Chandler Development Services)
Chandler Homeowner Building Permit Manual (Rev. 4/09/26), Gas Permits; 2024 IFGC Section 406 as adopted by City Code 29-7
“Tests of systems shall be performed at no less than 1-1/2 times the proposed maximum working pressure, but no less than 3 psig.”
Applies to:
Chandler homeowners (owner-applicants) and licensed contractors installing or extending gas piping at a home, natural gas or propane
In force:
2024 International Fuel Gas Code, adopted by Chandler City Code 29-7 (Ord. 5108, eff. 2025-07-01), since July 1, 2025
Last verified:
September 29, 2026, against the official page

A pressure test is how the city proves new gas pipe is tight before anyone puts gas in it. Chandler spells out its test in the homeowner manual, in five sentences. The surprise for people who have worked in other Valley cities is the number: Chandler's floor is 3 psig, while Mesa's is 10 psi.

What does the Chandler manual say about gas pressure tests?

Chandler requires a test at 1.5 times the system's maximum working pressure, with a floor of 3 psig. The Homeowner Building Permit Manual (Gas Permits) says: "Tests of systems shall be performed at no less than 1-1/2 times the proposed maximum working pressure, but no less than 3 psig."

The next sentence tells you which number most homes land on: "Most residential systems (including propane) will be at 3 psig unless you have a high-pressure system above 2.0 psi."

Then the timing and the setup. The manual says: "Test duration shall not be less than 10 minutes." It adds: "All tests must be made through the open valve and flex line." And: "The flex line must be capped at the appliance connection."

The parts, one at a time:

  • Pressure: 1.5 times the maximum working pressure, and never under 3 psig.
  • Typical home: 3 psig, natural gas or propane, unless the system runs above 2.0 psi.
  • Time: at least 10 minutes.
  • Setup: appliance valve open, flex line included, flex line capped where it meets the appliance.

Chandler adopts the 2024 International Fuel Gas Code in City Code 29-7, effective July 1, 2025. Its amendments there (29-7.1 and 29-7.2) replace Chapter 1 only, so the model code's testing section applies as published. The 2024 IFGC Section 406.4.1 sets the same 1.5 times and 3 psig rule, and Section 406.4.2 sets 10 minutes for "a system in a single-family dwelling."

What do the key terms mean?

  • psig: pounds per square inch, gauge. The reading on the test gauge.
  • Maximum working pressure: the highest pressure the gas system is designed to run at.
  • High-pressure system above 2.0 psi: the manual's term. The manual does not define it further. Our reading: 1.5 times 2.0 is exactly 3, which is why systems at or below 2.0 psi test at the 3 psig floor.
  • Flex line: the flexible connector from the gas valve to the appliance.
  • Test medium: what you pump into the pipe. The IFGC allows air, nitrogen, carbon dioxide or an inert gas.

Who does this cover?

It covers anyone putting in new gas piping at a Chandler home under a permit: a homeowner doing the work as owner-applicant, or a licensed contractor. The manual says a licensed contractor must do permitted work "unless the owner-applicant performs the work," and that if you rent the home to others, a licensed contractor is required to obtain the permit.

This does not apply the same way to every change. The IFGC (Section 406.1.2) says minor repairs and additions don't need a pressure test if the work is inspected and the connections are tested with a noncorrosive leak-detecting fluid or another approved method. Under Section 406.1.3, when new branches go to new appliances, only the new branches need the pressure test.

Quick check: what test does your job need?

SituationTestWhy
New line to a range, natural gas, normal house pressure3 psig for 10 minutes or moreManual: most residential systems test at 3 psig
Same job on a propane system3 psig for 10 minutes or moreManual names propane in the 3 psig sentence
System designed above 2.0 psiAt least 1.5 times its maximum working pressureManual: 3 psig applies "unless" the system is above 2.0 psi
Appliance already set with its flex lineTest through the open valve and flex line, flex capped at the applianceManual, Gas Permits
Pipe already buried or drywalledNot ready to inspectManual: work to be inspected "must be accessible and exposed"
Gauge drops during the testTreated as a leakIFGC 406.5, unless another cause is clear
New branch added to an existing systemOnly the new branch is pressure testedIFGC 406.1.3; the tie-in joint gets a leak-detecting fluid check

What does this look like in real life?

The range upgrade. A homeowner in Chandler adds a gas line for a new range off the existing house piping. The new branch is tested at 3 psig for at least 10 minutes, with the range valve open and the flex line capped at the appliance end. For the test to pass, the gauge has to hold.

The propane house. A home runs on a propane tank, not a gas meter. The answer does not change. The manual puts propane in the same 3 psig sentence.

The edge case: an elevated pressure system. Say a system is designed to run at 5 psi. That is above 2.0 psi, so 3 psig is no longer enough. The test has to be at least 1.5 times 5, which is 7.5 psig.

The crew from Mesa. A contractor who mostly works in Mesa is used to 10 psi, the floor in Mesa's amendments to the IFGC. Chandler's written floor is 3 psig. A 3 psig test that meets Chandler's manual would fall short in Mesa, so the city on the permit sets the number.

What should you do next?

  1. 1Get the gas permit first. The manual asks for a gas riser schematic from the meter with every appliance, its BTU rating, and each line size and type. Our Chandler gas line permit page covers that part.
  2. 2Leave every joint exposed. Don't bury or cover pipe that still needs its inspection.
  3. 3Set up the test: appliance valve open, flex line capped at the appliance connection, and air, nitrogen, carbon dioxide or an inert gas as the test medium.
  4. 4Bring the system to at least 3 psig, or 1.5 times the working pressure if it runs above 2.0 psi, and hold it at least 10 minutes. IFGC 406.4 limits mechanical gauges to a scale whose top end is no more than five times the test pressure. At 3 psig, that means a gauge that tops out at 15 psi or less.
  5. 5Book inspection 735 Rough Gas Piping Test at least one business day ahead, through CLICS at chandleraz.gov/clics, by phone at 480-782-3100, or by text to 844-281-3520 (S, permit number, 735, date). The city's list also has 736 Final Gas Piping Test and 746 Gas Final.
  6. 6Not sure your job needs a permit? The manual points those questions to the Plan Reviewer of the Day at 480-782-3078 or prod@chandleraz.gov.

What do people get wrong?

  • Myth: 10 psi is the number everywhere. Mesa's amended code says 10 psi. Chandler's manual sets a 3 psig floor.
  • Myth: close the appliance valve for the test. Chandler's manual says the test runs through the open valve and flex line, with the flex line capped at the appliance.
  • Myth: a small drop on the gauge is fine. The 2024 IFGC says: "Any reduction of test pressures as indicated by pressure gauges shall be deemed to indicate the presence of a leak unless such reduction can be readily attributed to some other cause."
  • Myth: any gas works as the test medium. The IFGC says: "Oxygen shall not be used as a test medium."
  • Myth: propane gets a different test. Not in Chandler. The manual includes propane at 3 psig.

What happens if you skip the permit?

The manual lists what the city can do about work done without a permit: issue a Legal Notice or an Order to Comply, and double the permit fees. It says Chandler can also order non-compliant work removed. The manual also says: "The building inspector must approve all work before construction can proceed to the next level."

This page explains Chandler's manual and the adopted 2024 IFGC as read on the date above; the official text and your inspector govern any specific job.

How Do Other Valley Cities Handle It?

WhereWhat appliesSource
MesaHigher floor. Gas piping is tested at not less than 10 psi gauge, or at least 6 inches of mercury where the building official approves. Welded piping and gas above 14 inches water column test at not less than 60 psi.Mesa City Code 4-7-2, IFGC 406.4.1 as amended (same test in 4-3-2, IRC G2417.4.1)
Verified September 29, 2026
PhoenixPhoenix's 2024 IFGC amendments change Chapter 1 and the Section 403.11 flange rules only. Section 406, the pressure test, is not in the amendment document.Phoenix amendments to the 2024 IFGC, Ord. G-7397 (eff. 2025-08-01)
Verified September 29, 2026
ScottsdaleScottsdale enforces the 2021 IFGC. Its amendments cover Chapter 1, a gas vent termination exception in Section 503.6.5 and the adopted appendices; none touch the pressure test.Scottsdale Revised Code Secs. 31-100 to 31-103
Verified September 29, 2026

This page explains the rule. The official text at the source above governs.

Sources

Gas Lines in Other Cities

More Chandler Codes and Permits

Related Rules and Questions

Questions About Chandler Plumbing Code?

We work to code every day across the Valley. Call the dispatcher and we'll tell you what your project needs.