Tempe's amended IPC 608.7.2 requires a reduced pressure backflow assembly at each point of service delivery for hospitals, surgical clinics, medical buildings, laboratories, morgues, veterinary hospitals, grooming shops, industrial occupancies, plants that handle food or chemicals, auxiliary water systems and construction water services. Interconnected services need at least a double check each.
“The following activities or facilities shall have a Secondary Reduced Pressure Principle Backflow Prevention assembly installed as close as practicable to each point of service delivery”
- Applies to:
- Owners, designers and plumbing contractors of hospitals, clinics, labs, industrial buildings and construction water services in Tempe
- Official fee:
- not applicable
- In force:
- 2024 International Plumbing Code with Tempe amendments (Tempe City Code 8-600; Ord. O2024.19, amended by Ord. O2026.24)
- Last verified:
- September 29, 2026, against the official page
Most people find Tempe's backflow rules in the water code. This one sits in the plumbing code, and it is written for the building official, not the water utility. It picks out the highest-hazard facilities and says one thing about all of them: a reduced pressure assembly at every service.
What does Tempe's IPC 608.7.2 say?
The model IPC has a section 608.7.2. Tempe replaced it with its own text: "The following activities or facilities shall have a Secondary Reduced Pressure Principle Backflow Prevention assembly installed as close as practicable to each point of service delivery: Hospitals, surgical clinics, medical buildings, laboratories, morgues, mortuaries, veterinary hospitals, animal grooming shops, industrial occupancies, packing plants, slaughter houses, chemical plants, municipal waste treatment facilities, auxiliary water systems, construction water services or as otherwise required by the City of Tempe Building Official."
A note follows: "Multiple water services which are interconnected onsite shall be provided with not less than a Double Check Valve Assembly at each service connection."
The parts:
- Who: the named facilities, plus anything the Building Official adds.
- What: a reduced pressure principle (RP) assembly.
- Where: as close as practicable to each point of service delivery, which means every service, not just the main one.
- Interconnected services: at least a double check at each, even if the facility is not on the list.
What do the key terms mean?
- Secondary: the code does not define it. Our reading is that it means protection at the service connection, over and above any protection built into the building's own equipment.
- Point of service delivery: where city water enters the property, usually the meter.
- Industrial occupancy: not defined in this section. It is a building-code classification, so the plans examiner decides.
- Auxiliary water system: a second water source on the property, such as a well or reclaimed line.
- Interconnected: two services tied together inside the property.
Who does this cover?
It covers new and altered buildings of the listed types and construction water services, which are temporary services for building sites. It does not cover a house or a facility not on the list, unless the Building Official adds it or another rule applies. The water code in 33-105 has its own overlapping table, and the stricter answer wins.
Quick check: is a secondary RP required?
| Facility | RP at each service? | Why |
|---|---|---|
| Hospital or surgical clinic | Yes | Named |
| Medical or dental building | Yes | "Medical buildings" |
| Veterinary hospital or grooming shop | Yes | Named |
| Morgue or mortuary | Yes | Named |
| Chemical or packing plant | Yes | Named |
| Construction water service | Yes | Named |
| Two services tied together inside a warehouse | At least a double check on each | Interconnected-services note |
| Restaurant | Not named here | Building Official can add facilities |
| Single-family home | No | Not listed |
What does this look like in real life?
A new outpatient clinic. Medical buildings and surgical clinics are named, so the plans need an RP at the point where each service enters.
A warehouse with two water services. Neither service is on the list, but the owner tied them together inside for fire and domestic supply. The note applies: a double check at each connection at minimum.
The edge case: a restaurant. The list does not name it, and the section leaves room for the Building Official to add facilities. Tempe's water code, 33-105, does not name restaurants either. Ask plan review before you assume it is exempt.
What should you do next?
- 1Compare your occupancy with the list above and with the 33-105 table.
- 2Put an RP on the plans at each point of service delivery, with the location marked.
- 3Keep it above ground. IPC 608.8.1 bars backflow devices in pits, underground vaults or submerged locations.
- 4The designer or contractor submits the plans with the building permit application to Tempe Building Safety (480-350-8341 is the permit number on the city's Backflow FAQ). The water code requires approval before the permit issues.
- 5After installation, have the assembly tested and inspected before the certificate of occupancy.
- 6Plan for a test every year after that.
What do people get wrong?
- "Secondary means optional." The code says these facilities "shall have" the assembly.
- "The meter has a check valve, so I am covered." The code calls for a reduced pressure assembly, not a meter check.
- "One assembly at the main covers everything." The requirement is at each point of service delivery.
- "Tempe and Phoenix use the same list." They overlap, but veterinary hospitals, animal grooming shops, industrial occupancies and packing plants are on Tempe's list only. Phoenix sends the rest to its own Chapter 37, Article XII.
How Do Other Valley Cities Handle It?
| Where | What applies | Source |
|---|---|---|
| Phoenix | The lists overlap but are not the same. Phoenix's amended IPC 608.7.2 lists hospitals, surgical clinics, medical buildings, laboratories, morgues, mortuaries, slaughter houses, chemical plants, municipal waste treatment facilities and auxiliary water systems and construction water services, and defers the rest to Phoenix City Code Chapter 37, Article XII. Veterinary hospitals, animal grooming shops, industrial occupancies and packing plants are on Tempe's list only. The interconnected-services note is identical. | Phoenix 2024 IPC amendment to 608.7.2 Verified September 29, 2026 |
| Scottsdale | Hospitals and mortuaries, animal clinics and grooming shops, chemical plants, food processing plants and more are on the utility code's RP list. Restaurants and beauty shops are named too. | Scottsdale Revised Code 49-62 Verified September 29, 2026 |
This page explains the rule. The official text at the source above governs.
Backflow Prevention in Other Cities
- ChandlerChandler backflow testing: annual test, notices and water shutoff
- ChandlerChandler City Code 52-36: backflow assemblies on commercial building plans
- GilbertGilbert Town Code 10-92(c): which backflow assembly does your kind of property need?
- GlendaleGlendale City Code 33-90: which businesses need a backflow device
- GlendaleGlendale City Code 33-92: backflow devices on fire sprinkler services
- GlendaleGlendale City Code 33-94: annual backflow test, records and shutoff
More Tempe Codes and Permits
- Backflow PreventionStolen or moved backflow assembly in Tempe: replacement and permit
- Backflow PreventionTempe City Code 33-103 and 33-104: backflow assemblies on plans and how to install them
- Backflow PreventionTempe City Code 33-105: which commercial properties need a backflow assembly?
- Backflow PreventionTempe City Code 33-107: backflow assemblies must be tested every year
- Sewer LinesTempe City Code 27-175: who owns and repairs the sewer line, even under the street?
- Commercial PlumbingTempe City Code 27-22: grease traps, interceptors and the garbage disposal ban
Related Rules and Questions
- UPCUPC Section 603: Cross-Connection Control and Backflow Protection
- ArizonaArizona Administrative Code R18-4-215: Backflow Prevention and Annual Testing
- FAQRPZ vs double-check backflow assembly: what's the difference?
- FAQWhat is a cross-connection and why is it dangerous?
- FAQHow often does a commercial backflow preventer need testing in Arizona?
- Commercial Plumbing