The developer or owner who needs service pays to design, permit and build the main, then deeds it to the city. Phoenix says so in City Code Chapter 28, and Mesa requires an 8-inch main across the whole frontage (8-10-4). Five cities, including Phoenix, let you recover part of the cost from neighbors who connect later.
“The developer must pay for all the costs to design, permit, and construct the sewer main extension, including any costs of acquiring rights-of-way and easements”
- Applies to:
- Developers, commercial property owners, general contractors and civil engineers bringing water or sewer service to a new building or pad
- In force:
- Each city's water and sewer code; A.A.C. R18-5-505 and R18-9-E301 for state approvals
- Last verified:
- October 4, 2026, against the official page
What Does Each Valley City Require?
| Where | What applies | Source |
|---|---|---|
| Phoenix | Developer hires an Arizona-registered civil engineer and pays to design, permit and build a sewer main extension, including right-of-way, as-builts and city inspection. Any lift station is at the developer's expense. Repayment agreements need three sealed bids. | Phoenix City Code Ch. 28, Art. III Verified October 4, 2026 |
| Mesa | To get water service, extend at least an 8-inch distribution main along the entire frontage (every frontage on a corner lot) and loop transmission mains the Water Master Plan calls for. Title goes to the city, and the customer grants the needed easements at no cost. | Mesa City Code 8-10-4 Verified October 4, 2026 |
| Scottsdale | Before connecting, install at least an 8-inch water or sewer main along the entire frontage if required. Payback agreements for lines serving single-family property need approved plans and three independent bids 30 days before construction, and the owner cannot be the contractor. | Scottsdale Revised Code 49-215 and 49-219 Verified October 4, 2026 |
| Chandler | The city may share in a water main contract, with the developer bidding it like a public works job. A developer whose main can serve others may sign a reimbursement agreement within one year of acceptance, running up to 15 years. | Chandler City Code 52-23 and 52-24 Verified October 4, 2026 |
| Gilbert | Developer pays in full for right-of-way, construction, town and state permit fees and taxes, plus any street, curb and sidewalk repair. Minimum pipe: 12 inches on section lines, 8 on half-section lines, 6 elsewhere; the town can require larger. Council accepts the finished main. | Gilbert Town Code 10-292, 10-294 and 10-295 Verified October 4, 2026 |
| Glendale | Extension reimbursement agreements are allowed inside the city only, with competitively bid construction. Later users pay their share before getting a connection permit; water lines split by footage, sewer by acreage, and the developer's own share is never reimbursed. | Glendale City Code 33-271 to 33-281 Verified October 4, 2026 |
| Surprise | The city reserves the right to install any water main extension. A developer who causes one pays in full for right-of-way and construction and gives up all interest on acceptance; a repayment agreement is available when the main will serve future developers. | Surprise Municipal Code 58-211 Verified October 4, 2026 |
If the nearest water or sewer main stops short of your property, first ask the utility whether an extension is required. The codes compared here generally place extension costs on the developer, subject to each city's construction, cost-sharing and acceptance provisions. What differs is how far you have to build, whether the city chips in for oversizing, and whether you can get some of the money back when the neighbors hook up.
What does Phoenix's sewer code say about main extensions?
Phoenix's Chapter 28, Article III is blunt: "The developer must pay for all the costs to design, permit, and construct the sewer main extension, including any costs of acquiring rights-of-way and easements." The same section adds the as-built plans and the city's own inspection to the developer's bill. The Director decides the layout and pipe size for peak flow, and if gravity won't work, the developer builds the lift station too.
Once the city accepts the work, the main is public. You paid for it, but you don't own it, and the article says no owner keeps "a legal or equitable right or interest" in it.
Common requirements in these extension provisions include:
- You pay: design, permits, right of way or easements, construction, inspection, and the street repair afterward.
- You build to their standard: city details and specifications, with the pipe size set by the city.
- You hand it over: title transfers on acceptance.
- Some cities pay back: Phoenix, Chandler, Glendale, Scottsdale and Surprise have agreements to recover part of the cost from later connectors. Phoenix's sewer repayment program wants at least three sealed bids before the city accepts the project and pays no interest.
What do the key terms mean?
- Main extension. New public water or sewer main laid to reach a property the system doesn't serve yet. Different from a service line or lateral, which runs from the main to one building.
- Frontage rule. Mesa and Scottsdale make you run the main along the entire street frontage of your parcel, not just to your tap, so the next lot can connect.
- Oversizing. When the city wants a bigger pipe than your project needs. Chandler and Scottsdale have code sections for the city sharing that extra cost.
- Payback, reimbursement or repayment agreement. A contract where the city collects a share from later users of your main and passes it to you.
- Approval to Construct. The state (ADEQ) sign-off to build or extend a public water system, under A.A.C. R18-5-505.
Who does this cover?
Anyone extending a public water or sewer main: developers, commercial owners building on an unserved pad, and owners converting from septic or a private well where the main is down the road. It also covers the engineers who design the line.
It does not apply to a single building's own service line or lateral from an existing main. ADEQ's sewage collection general permit specifically excludes "a gravity sewer line conveying sewage from a single building drain directly to" a sewer.
Quick check: what will your project need?
| Your project | Likely requirement | Why |
|---|---|---|
| New retail pad in Mesa, water main ends at the next parcel | Extend an 8-inch main across your whole frontage | Mesa 8-10-4(A) |
| Corner lot in Scottsdale | Main along both frontages may be required | Scottsdale 49-219 |
| Pad in Phoenix below the sewer's gravity line | Build a lift station at your expense | Phoenix Ch. 28, Art. III |
| Main you build will serve three future parcels in Glendale | Ask for a reimbursement agreement with the extension permit | Glendale 33-274 |
| Chandler main accepted 14 months ago, no agreement yet | Too late for reimbursement | 52-24(B) one-year window |
| Public water main extension | Ask ADEQ or its delegate for the applicable Approval to Construct/plan-review process and any qualifying small-project exception | A.A.C. R18-5-505(B)(2)-(4) |
| New sewer with a manhole, or a lift station serving more than one dwelling | ADEQ 4.01 general permit | A.A.C. R18-9-E301(A) |
| One building's lateral straight to an existing sewer | No 4.01 permit | The single-building-drain exception |
What does this look like in real life?
A medical office on a Gilbert half-section line. The water main has to be at least 8 inches, but the town can require bigger "if deemed advisable by good engineering practices." The developer also pays for the curb and sidewalk repairs the trench causes.
A Scottsdale owner who wants to be their own contractor. For a payback agreement on a line serving single-family property, Scottsdale requires three independent bids and says the developer or owner "cannot act as the Contractor." Skip the agreement and that restriction doesn't bite, but neither does the payback.
A Glendale developer whose neighbor connects first. The city collects the neighbor's allocated share before issuing their connection permit, then reimburses the developer from a trust account. The developer's own share of the pipe is never paid back.
The same project outside Glendale's limits. No agreement is possible: the code bars reimbursement agreements for extensions outside the city.
What should you do next?
Settle the extension before the building plans, since it drives both schedule and cost.
- 1Ask the water and sewer utility where the nearest main is, what size it is, and whether it has capacity for your flows.
- 2Hire an Arizona-registered civil engineer. Phoenix requires one for sewer extensions, and the state rule normally requires a sealed design for water, with limited small-project provisions in R18-5-505(B)(2)-(4).
- 3Get the ADEQ approvals in line: an Approval to Construct for water, and a 4.01 general permit when R18-9-E301 covers the sewer system. Its triggers include a manhole, a shared force main/lift station, and the specified 3,000-gpd design-flow threshold, subject to the single-building gravity-line exclusion.
- 4File the extension permit with the city, and in Glendale or Chandler the reimbursement request at the same time.
- 5Bid the work the way the city requires. Chandler and Glendale call for public-works style competitive bidding when the city shares cost or reimburses.
- 6Build, pass inspection, and convey the main free of encumbrances, then pull the tap and connection permits.
What do people get wrong?
- "The city extends mains when new customers ask." Not in these codes. Surprise reserves the right to build one, but the developer who causes it still pays in full.
- "We only need pipe to our tap." Mesa and Scottsdale require it along your entire frontage unless the city waives it.
- "Payback is automatic." Phoenix wants three sealed bids before acceptance, Chandler's window closes one year after acceptance, and Glendale needs the request filed with the extension permit.
- "A plumbing permit covers it." Main extensions are civil work with separate city permits and state approvals; the plumbing permit covers the building side.
What happens if you skip it?
ADEQ's rule says a person "shall not start to construct" an extension to a public water system before receiving an Approval to Construct. Mesa won't provide service through a main built by others until title is tendered and the city accepts it, and Gilbert's council must accept the extension before it can be used.
When the main is in and you need the building's taps, service lines and laterals built, HQ can help with building water and sewer lines. Public-main extensions require a separate civil design, utility approval and a contractor authorized for that work.
This page explains the rule. The official text at the source above governs.
- Mesa City Code 8-10-4, Minimum Requirements for Potable Water Service (Municode)
- Arizona Secretary of State, Title18 Chapter5: R18-5-505, Approval to Construct
- Arizona Secretary of State, Title18 Chapter9: R18-9-E301, Sewage Collection Systems
- Glendale City Code Chapter 33, Article V, Extension Reimbursement Agreements (Municode)
Water Supply and Pipes in Other Cities
- ChandlerChandler water meter installation fee: 50-9 schedule by meter size
- El MirageEl Mirage City Code 50.066: who installs water taps and service lines?
- MesaWho pays for a new commercial water service in Mesa? Main extension, meters and easements under City Code 8-10-3 and 8-10-4
- PhoenixCan you use PVC, CPVC or PEX water pipe outdoors in Phoenix?
- PhoenixWho is responsible for the water line to your Phoenix property, the city or you?
- TempeTempe water tap and development fees by meter size for commercial service
More Valley-Wide Codes and Permits
- Commercial PlumbingWhich Businesses Need a Backflow Assembly in Each Valley City
- Gas LinesGas Line Permits in Each Valley City
- Gas LinesGas Line Burial Depth Rules in Each Valley City
- Gas LinesGas Line Pressure Test Rules in Each Valley City
- Gas LinesGetting Gas Turned On After Inspection in Each Valley City
- Commercial PlumbingGrease Interceptor Records and Inspections by Valley City
Related Rules and Questions
- Valley-WideRight-of-Way Permits for Plumbing Work by Valley City
- Valley-WidePavement Cut and Street Restoration Rules by Valley City
- Valley-WideWho Owns the Sewer Line From the Building to the Main, by City
- UPCUPC Section 720: The Required Gap Between Water and Sewer Lines
- UPCUPC Section 604: Approved Materials for Water Pipe
- FAQHow much is the sewer connection fee for a new home in Phoenix?
- FAQHow do I convert from septic to city sewer in Phoenix?
- FAQWhat is a sewage lift station and how do you maintain it?
- FAQDo I need a permit to dig in the street right-of-way to fix my sewer or water line in Phoenix?
- Sewer Repair & Installation
